DEMO Packaging & Production Scheduler — Model Scoping

Status: scoping only. No model is being built in this document. The goal is to make explicit what is being decided, over what dimensions, with what knobs, and where the data is missing.

All cardinalities below come from the 2025 PoC dataset (Packaging Ampoules.xlsx, sheet BO & FC 2025).


1. Index sets — the "levels" the model will reason over

Set Symbol Size (2025 PoC) Source Notes
Demand lines (orders) o ∈ O 1,824 BO & FC 2025 rows Each row = (Country/Customer × Material × line × format × quarter triplet).
Materials / SKUs s ∈ S 240 distinct material numbers (266 descriptions) Material Number Description varies by country labelling — needs canonical key.
Customers / countries c ∈ C 38 Country column Mixed entities: countries (UK, GR), customers (Piramal, Pharmathen), organizations (Unicef, MSF, ICRC). Needs canonical taxonomy.
Customer classifications k ∈ K ~3 (ISD, GR, …) Ranking sheet Coarse channel grouping.
Packaging lines m ∈ M_pack 4 packaging line column Marchesini GL, Farcon, Dividella, Partena.
Production lines / stages m ∈ M_prod TBD MISSING Tank, filling, etc. (req #28 mentions stages).
Formats (mould / volume) f ∈ F 5 Mould / Volume 0002ml, 0003ml, 0005ml, 0010ml, 0020ml.
Container types g ∈ G 2 expected (Glass, Plastic) inferred from PPT Needed for the changeover-only-on-container-change rule (req #33).
Time buckets — weeks w ∈ W 52 (req #17) calendar Atomic scheduling unit for packaging.
Time buckets — months t ∈ T 12 calendar Required for Piramal monthly band (req #37).
Time buckets — quarters q ∈ Q 4 + BO calendar Used for tier-1 feasibility (req #27).
Shifts h ∈ H up to 3 / day, 5 days / week configurable Packaging cycles run weekly (req #18).
APIs (active ingredients) a ∈ A TBD MISSING explicit list — derivable from material BoM Drives the "one API per production week" rule (req #42).
Customer-product rating classes r ∈ R 35 final-factor combos + VIP flag Final Factor, VIP XYZ + delay grade n per the PPT.

Total dimensionality of the raw schedule space (orders × lines × weeks): 1,824 × 4 × 52 ≈ 380 k cells for packaging, plus an analogous production layer. Tractable for MILP/CP after symmetry breaking and pre-filtering by line eligibility.


2. Decision variables

Packaging schedule (the primary output)

Variable Indices Domain Cardinality (PoC) Meaning
x_pack[o, m, w] order × pack-line × week binary ≤ 380 k Order o packaged on line m in week w.
y_pack[m, f, w] line × format × week binary 4 × 5 × 52 = 1,040 Line m is configured for format f in week w (campaign indicator — at most one per (m,w)).
co_pack[m, f1, f2, w] line × from-fmt × to-fmt × week binary 4 × 5 × 5 × 52 = 5,200 Format changeover on line m at the boundary of week w.
vol_pack[o, w] order × week continuous ≥ 0 1,824 × 52 ≈ 95 k Units of order o packaged in week w (allows multi-week orders).
start_pack[o] order integer week 1,824 First week order o enters packaging.
late[o] order continuous ≥ 0 1,824 Lateness of order o (weeks past due[o]).
unfilled[o] order continuous ≥ 0 1,824 Unmet demand of order o.

Production schedule (semi-finished)

Variable Indices Domain Cardinality (PoC) Meaning
x_prod[s, m, w] semi-fin × prod-line × week binary TBD Semi-finished s produced on line m in week w.
qty_prod[s, w] semi-fin × week continuous ≥ 0 240 × 52 ≈ 12 k Quantity of s produced in week w (planned, after scrap/yield req #47).
api_active[a, w] API × week binary |A| × 52 The "one API per week" indicator (req #42).
evaton_batch[w] week binary / int 52 Special rule for semi-fin "T" / EVATON: 2 batches at a time, ≥3-week gap (req #49).

Inventory and linkage

Variable Indices Domain Meaning
inv[s, w] semi-fin × week continuous ≥ 0 End-of-week stock of s.
expire[s, w] semi-fin × week continuous ≥ 0 Stock written off due to shelf-life cap (req #48).
prod_to_pack_lag[o] order integer days ≥ 4 days, packaging after production (req #46).
prod_to_label_lag[o] order integer days ≥ 3 days.

Auxiliaries used by the objective

Variable Meaning
idle_hours[m, w] unused machine-hours (penalised).
tie_split_dev[c] deviation from fair-share when two customers tie on score (req #40).
piramal_dev[t] deviation of Piramal monthly volume from band centre (req #37).

3. Parameters (model inputs)

Available now (in the Excel)

Parameter Indices Source Cardinality
demand[o, q] order × quarter Q1 2025, Q2 2025, Q3 2025, Q4 2025 columns 1,824 × 4
bo[o] order BO 2024 column 1,824
pack_slots[o, q] order × quarter Pack slot Q1..Q4 1,824 × 4
points[o, q] order × quarter Point Q1..Q4 1,824 × 4
total_qty[o] order Total Quantity for packaging 2025 1,824
format[o] order Mould / Volume 1,824
assigned_line[o] order packaging line (current manual choice) 1,824
final_factor[o] order Final Factor (35 classes) 1,824
vip[o] order VIP (10000 or null) 1,824 (73 set)
rating_factor_1/2/3[o] order 1st/2nd/3rd Rating Factor (A–D) 1,824
rating_point_1/2/3[o] order 1st/2nd/3rd Rating Point 1,824
customer_class[c] customer Ranking sheet 38
region[c] customer Ranking sheet 38
is_org[c] customer derived (Unicef/Imres/ICRC/IDA flag) 38
mode_line_total[g] mode line ISD Forecast Totals 2025 10

Required but NOT in the Excel — see §8

changeover_h[m, f1, f2], throughput[m, f], shift_calendar[m, w], maintenance[m, w], bom[s, raw], material_avail[raw, w], shelf_life[s], scrap_rate[s], due_date[o], min/max_batch[s].


4. Knobs — user-tunable parameters (req #1, #4, #9)

These must be configuration, never hard-coded:

Knob Type Default (suggested) Affects
w_fulfilment objective weight 1.00 demand fulfilment term
w_changeover objective weight 0.10 changeover-time penalty
w_idle objective weight 0.05 idle-hours penalty
w_tie_split objective weight 0.20 fair-distribution bonus (req #40)
vip_multiplier rating multiplier 10,000 VIP rows (matches Excel)
delay_step rating increment per missed window 1 the n in n + XYZ
XYZ_weights[X,Y,Z] per-axis weight configurable A/B/C/D order ranking
piramal_min_month / piramal_max_month hard / soft band 1.8 M / 2.0 M req #37
prod_to_pack_min_lag days 4 req #46
prod_to_label_min_lag days 3 req #46
campaign_coverage_24mo / _36mo months 6 / 9 req #45
glass_machine_pick_rule function by volume thresholds req #31, #32
farcon_dividella_lock bool true req #35
team_changeover_no_overlap bool true req #36
evaton_min_gap_weeks int 3 req #49
horizon_weeks int 52 req #17
shifts_per_day, days_per_week int 3, 5 calendar
working_hours_per_shift hours 8 calendar
holidays[w], maintenance_blocks[m,w] calendar from input req #5

5. Constraints — mapped to variables and parameters

Hard

# Constraint (req #) Formal sketch
1 One format per (line, week) — each format max once per cycle (#8) Σ_f y_pack[m,f,w] ≤ 1 for each (m,w)
2 Demand fulfilment Σ_w vol_pack[o,w] + unfilled[o] = total_qty[o]
3 Order ↔ machine eligibility x_pack[o,m,w] = 0 if m ∉ eligible(o)
4 Glass-machine selection by volume (#31, #32) range constraints vol[o] ∈ band(m)
5 Org orders not split (#39) Σ_w x_pack[o,*,w] = 1 if is_org[customer(o)]
6 Piramal monthly band (#37) 1.8M ≤ Σ_{o ∈ Piramal} Σ_{w ∈ month(t)} vol_pack[o,w] ≤ 2.0M
7 Farcon XOR Dividella (#35) y_pack[Farcon,*,w] + y_pack[Dividella,*,w] ≤ 1
8 No overlap of changeover team (#36) Σ_m co_pack[m,*,*,w] ≤ 1 per w
9 Production → packaging lag ≥ 4d (#46) start_pack[o] ≥ end_prod[o] + 4 days
10 Production → labeling lag ≥ 3d (#46) analogous
11 One API per production week (#42) Σ_a api_active[a,w] ≤ 1
12 Campaign coverage by shelf life (#45) linkage between qty_prod[s,w] and demand aggregates over 6 / 9 mo
13 Shelf-life storage cap (#48) vol_pack[o,w] ≤ inv[s,w-shelf_life[s]] style
14 EVATON 2-batch / 3-week gap (#49) Σ_{w'∈[w,w+3)} evaton_batch[w'] ≤ 1
15 Capacity (machine-hours) Σ_o vol_pack[o,w]/throughput[m,f] + changeover_h ≤ avail_h[m,w]

Soft (penalties on objective)

  • Tie-fairness — tie_split_dev[c] (#40)
  • Schedule highest-score weeks first (#41)
  • Minor format changes — small fixed cost (#38)

6. Objective function

maximize
    w_fulfilment   · Σ_o rating_score[o] · (total_qty[o] − unfilled[o])
  − w_changeover   · Σ_{m,f1,f2,w} co_pack[m,f1,f2,w] · changeover_h[m,f1,f2]
  − w_idle         · Σ_{m,w} idle_hours[m,w]
  − w_tie_split    · Σ_c tie_split_dev[c]
  − w_late         · Σ_o late[o]

rating_score[o] = vip_multiplier · vip[o] + Σ_i rating_point_i[o] + delay_step · n[o] (per the PPT logic).


7. What we need to solve — in plain English

The job is to take the 1,824 demand lines for 2025 and produce two interlocked schedules:

  1. Packaging schedule — for every order, pick (line, week, format) so that:
    • high-rated and VIP customers come first,
    • Marchesini GL (61 % of demand) doesn't blow capacity,
    • Farcon and Dividella never run at the same time,
    • format changeovers are minimised and never overlap,
    • the Piramal monthly band is respected,
    • organization orders (Unicef / Imres / ICRC / IDA) are not split,
    • and on ties, fulfilment is spread across customers rather than all-or-nothing.
  2. Production schedule — upstream, decide which API runs each week, in what campaign size, so that:
    • one API per week (with second only if first doesn't fill the week),
    • shelf-life-aware campaign coverage (6 mo for 24-mo SL, 9 mo for 36-mo SL),
    • production finishes ≥ 4 days before packaging,
    • EVATON's special 2-batch / 3-week-gap rule is respected,
    • scrap / yield is built into planned quantity.

Two coupling layers tie them: inventory of semi-finished (production output → packaging input) and time lag (packaging starts ≥ 4 days after production).


8. How we propose to solve it

A two-tier decomposition (matches req #27):

  • Tier 1 — Annual feasibility ranking. A lightweight LP / greedy that uses only total_qty[o], rating_score[o], and rough machine-hour budgets per quarter to confirm or reject each order. Output: the set O* ⊆ O and an annual envelope. Fast (seconds) and runs at the start of each rolling-horizon cycle.
  • Tier 2 — Quarterly MILP / CP-SAT. Full assignment for O* over 13 weeks at a time with all constraints from §5. Solver candidates:
    • PuLP + CBC — cleanest for the linear core (capacity, fulfilment, Piramal band).
    • OR-Tools CP-SAT — strongly preferred for the sequencing layer (changeovers, no-overlap of changeover team, sequence-dependent setup, EVATON gap). CP-SAT also natively expresses interval/no-overlap, which is awkward as MILP.
    • Likely hybrid: solve the assignment LP in PuLP, lock the line/week selection, hand sequencing to CP-SAT.

A what-if runner (req #15) re-runs Tier 2 with knob overrides without touching Tier 1, so users can A/B test parameter changes.

A re-schedule trigger (req #3, #7, #16) re-solves a partial Tier-2 problem when Photocells reports a slowdown ≥ threshold; the only new variable is "remainder of in-flight order: continue here or move to next cycle".

We will not start any of this until the gaps in §9 are closed.


9. Missing inputs — gap log

Sorted by blocking severity. Without these, the optimizer cannot be built.

Gap Required for Severity Likely source
Format-changeover times per packaging line, per (f1, f2) pair constraint #15, objective changeover term Blocker DEMO industrial-engineering team; the file naming led us to believe these were in Marchesini / FARCON-DIVIDELLA / Partena sheets, but those are demand pivots.
Throughput (units / hour) per packaging line × format constraint #15 (capacity) Blocker ProdAction (req #6).
Shift / maintenance calendar per machine × week capacity (#5) Blocker Internal HR / maintenance plan.
Bill of Material per finished product → semi-finished → API production tier, BoM availability check (#26) Blocker for Tier-1 Master data; mentioned as "to be defined" in req #26.
Material availability per raw material × week feasibility (#26, #27) Blocker for Tier-1 SAP.
Shelf life per semi-finished constraint #13 (#48), campaign size (#45) High Master data.
Scrap / yield rate per semi-finished planned-qty calc (#47) High ProdAction.
Due date / pack-slot calendar per order late[o], start_pack[o] lower bound High Pack-slot columns exist in BO&FC but are slot counts, not dates. Need a date table.
Glass machine selection rule (volume thresholds) constraint #4 (#31, #32) Medium Stated as a rule in PPT/req but exact thresholds undocumented.
Production-line set + stages production tier (#28) Medium M_prod is currently empty.
API → semi-finished mapping constraint #11 (#42) Medium Derivable from BoM once available.
Customer canonicalisation (UNITED KINGDOM - TROTWOOD vs United Kingdom; Pharmathen trailing space) clean joins to ratings Low (data hygiene) Internal.
Piramal entity definition constraint #6 (#37) Clarification The 32.9 M Piramal demand exceeds 1.8–2.0 M every month — confirm whether this is a per-entity or aggregate band.
Photocells / ProdAction integration spec re-schedule trigger (#3, #7, #16) Deferred API contract from those platforms.

10. Open questions for the client

  1. Piramal band scope — per legal entity, per ship-to, or aggregate?
  2. Backup-line policy — when Marchesini overflows, which line is the documented fallback (#9 mentions configurable backup)?
  3. VIP weight — is 10000 a literal points value or a flag we should translate?
  4. Customer-product rating periodRanking GR shows period 01.01.2024 – 31.12.2024; do we re-rate for 2025 or carry forward?
  5. Mode-line scope of the optimizer — start with Glass Ampoules only (this Excel), or extend to Plastic Ampoules / Bottles / Lyophillized in the same model?
  6. What-if storage — do scenario runs need to be persisted (audit trail) or are they ephemeral?

Glossary / Abbreviations

Acronym Expansion / Meaning
API Active Pharmaceutical Ingredient — drives the "one API per production week" rule (req #42).
BO Back Order — unfulfilled 2024 demand carrying into 2025 (BO 2024 column).
BoM Bill of Materials — finished-product → semi-finished → API decomposition.
CBC COIN-OR Branch and Cut — open-source MILP solver.
CP-SAT Constraint Programming-SATisfiability solver (Google OR-Tools); used for sequencing layer.
EVATON A specific semi-finished product class with the 2-batch / 3-week-gap rule (req #49).
GR Greece (domestic channel, also a sheet name).
HiGHS High-performance LP/MIP solver (open-source).
HR Human Resources.
ICRC / IDA / Imres / Unicef / MSF Humanitarian organisations whose orders cannot be split (req #39).
IIS Irreducible Infeasible Subsystem — minimal subset of constraints whose conflict makes the model infeasible.
ISD International Sales Division (the export channel).
LP Linear Programming.
MILP Mixed-Integer Linear Programming.
MiniZinc Declarative constraint-modelling language (solver-agnostic).
OR-Tools Google's open-source operations-research toolkit (CP-SAT, LNS, etc.).
PoC Proof of Concept (this 2025-data exercise, per req #34).
PuLP Python LP/MIP modelling library; talks to CBC, Gurobi, HiGHS, etc.
Pyomo Python algebraic modelling language for optimisation.
Q1 / Q2 / Q3 / Q4 Calendar quarters.
SAP The ERP system (DEMO's master-data and order-of-record).
SKU Stock Keeping Unit (here: SAP Material Number).
TBD To Be Determined — placeholder for inputs not yet sourced.
VIP Very-Important flag (weight 10,000 in the rating).
XYZ Three-axis customer-product rating: X = on-time/in-full, Y = order flexibility, Z = profitability tier.