DEMO Production & Packaging Scheduler — Problem Statement & End-to-End Approach

Companion documents:

  • README.md — project overview and data analysis
  • MODEL_SCOPING.md — index sets, decision variables, parameters, gap log
  • PROPOSED_SOLUTION_ARCH.md — 4-layer architecture (User / Agent / Tool / Data) with LangGraph supervisor, specialist sub-agents, and MCP-served solver and data services

1. Problem statement

1.1 In one paragraph

DEMO operates a multi-line glass-ampoule packaging facility. Each year ~2,000 demand lines must be assigned to a (packaging line, week, format) slot, upstream of a production plan that decides which API runs on which week, with shelf-life-aware campaign sizing, sequence-dependent format changeovers, customer-volume bands (Piramal 1.8–2.0 M/month), and team-shared changeover labour that prevents two machines changing format at the same time. Demand is concentrated (Piramal alone is 36 %), one line (Marchesini GL) carries 61 % of volume, and 4 % of orders are VIP-flagged with a multiplier large enough to reorder the whole plan. The 50 numbered requirements in Requirements EN.pdf define what correctness looks like; reproducing them by hand in Excel is what DEMO does today.

1.2 Formal statement (compact)

Given:

  • index sets O, S, C, M_pack, M_prod, F, G, W, T, A, R (see MODEL_SCOPING.md §1, with cardinalities |O|=1,824, |S|=240, |M_pack|=4, |F|=5, |W|=52 for the 2025 PoC);
  • parameters demand[o,q], total_qty[o], format[o], rating fields, customer metadata, bo[o], plus the inputs flagged in §9 of MODEL_SCOPING.md (changeover times, throughput, shift calendar, BoM, shelf life, scrap, due dates) — currently missing;
  • knobs Θ (rating weights, band edges, lags, calendar, …);

find decisions X = (x_pack, y_pack, co_pack, vol_pack, x_prod, qty_prod, api_active, inv, …) that

maximize     w_fulfilment · Σ_o rating_score(o,Θ) · (total_qty[o] − unfilled[o])
           − w_changeover · Σ co_pack[m,f1,f2,w] · changeover_h[m,f1,f2]
           − w_idle       · Σ idle_hours[m,w]
           − w_tie_split  · Σ_c tie_split_dev[c]
           − w_late       · Σ_o late[o]
subject to   the 15 hard constraints in MODEL_SCOPING.md §5
             over horizons   annual ⊃ quarterly ⊃ weekly ⊃ real-time

1.3 Why it is hard

Hardness source Concretely
Combinatorial core Sequence-dependent setup + no-overlap on shared changeover team is NP-hard even single-machine.
Multi-stage coupling Production must finish ≥ 4 days before packaging and respect shelf-life storage caps — production decisions can render packaging plans infeasible weeks later.
Multi-horizon coherence Annual ranking (req #27) must agree with quarterly confirmation, which must agree with weekly sequencing — the same data viewed at four resolutions.
Live re-planning Photocells reports a slowdown / freeze (req #16) → the plan from yesterday is stale, but the tail is still good — full re-solve wastes work.
Constraints are not static Sales adds VIP overlays, regulators change shelf life, mould changes alter formats. The list of constraints is itself an artefact under change control.
Stakeholder reasoning load When a plan changes, Production needs the shift view (#13), Sales needs the order-tracker view (#14), Production team wants what-ifs (#15), and Compliance wants the audit. The same answer needs three different explanations.

1.4 The four horizons that must stay coherent

                                      ┌──────────────┐
                                      │  ANNUAL      │  capacity envelope, order-rank, BoM availability
                                      │  (~52 wk)    │  → confirms feasible set O*
                                      └──────┬───────┘
                                             │ feeds into
                                      ┌──────▼───────┐
                                      │  QUARTERLY   │  full MILP for ~13-week chunk
                                      │  (~13 wk)    │  → assignment + campaign sizing
                                      └──────┬───────┘
                                             │ feeds into
                                      ┌──────▼───────┐
                                      │  WEEKLY      │  CP-SAT sequencing with sequence-dep setups
                                      │  (~5–7 d)    │  → exact timeline + Gantt
                                      └──────┬───────┘
                                             │ feeds into
                                      ┌──────▼───────┐
                                      │  REAL-TIME   │  LNS repair on disruption
                                      │  (minutes)   │  → patched schedule, not full re-solve
                                      └──────────────┘

2. Approach overview — three-tier hybrid

The optimizer alone is not the product. The product is an agent-orchestrated optimizer in which large language models reason about constraints and explanations, while the solvers do what they do best — search.

LAYER A.  DECLARATIVE MODEL                       (the "what")
            MiniZinc + Pyomo, plus a Constraint Catalog
LAYER B.  SOLVER ENSEMBLE                         (the "how, fast")
            MILP master (HiGHS / Gurobi)
            CP-SAT sub-solver (OR-Tools)
            LNS repair (OR-Tools)
            Discrete-event simulator (validation)
LAYER C.  AGENT ORCHESTRATION                     (the "why, what-if, what-now")
            LangGraph supervisor + 6 specialist agents
            Each tool is an MCP server, with a verifier-in-the-loop

LLMs do not solve the optimization problem. They translate, explain, validate, and bridge — the solver is still the source of truth for any number that ends up in SAP.


3. How constraints are modeled

3.1 Constraint catalog as the spine

Every constraint is a row in a versioned Constraint Catalog, served by the Master-Data MCP service:

field example
id C-037
requirement_ref req #37
nl_description "Piramal must receive between 1.8M and 2.0M ampoules per calendar month."
category customer_band
formal_expr forall t in T: 1_800_000 ≤ sum(o in O_piramal, w in month(t)) vol_pack[o,w] ≤ 2_000_000
parameters {piramal_min: 1_800_000, piramal_max: 2_000_000}
solver_layer MILP_master
severity hard
owner Sales / Account Mgr
version 2026-05-07.v3
verifier_state passed

The MiniZinc / Pyomo model is generated from the catalog at solve time, not hand-written. This makes "Piramal raises the band to 2.5 M" a one-row edit, not a code change.

3.2 NL → formal pipeline

User says: "Piramal can absorb up to 2.5M/month from Q3 onwards"
        │
        ▼
Constraint-Elicitation Agent
  ├── Parses to {entity: Piramal, dim: month, op: ≤, value: 2.5M, scope: Q3..Q4}
  ├── Drafts catalog row patch (id reuse if amending)
  └── Renders MiniZinc fragment
        │
        ▼
Verifier-in-the-loop
  ├── Schema check    — fields, types
  ├── Unit check      — 2.5M is "ampoules/month", not "boxes/week"
  ├── Solver-feasibility check — inject into a *cached* warm-started model, see if SAT
  └── Business-rule check     — Q3..Q4 cannot loosen if a contract says fixed
        │
        ▼
Catalog write (with diff vs prior version)
        │
        ▼
Re-solve trigger queued

If any verifier step fails, the agent narrates the failure to the user and offers an amendment — it never writes a broken constraint to the catalog.

3.3 Constraint categories and where they live

Category Solver layer Modelling pattern Example req
Demand fulfilment MILP master Linear Σ vol = total_qty − unfilled #2, #10
Capacity MILP master Σ qty / throughput + setup ≤ avail_h #5, #19
Customer bands MILP master Linear two-sided bound per month #37
Order indivisibility (org) MILP master Big-M or single-week assignment #39
Format-once-per-cycle MILP master Σ_w y[m,f,w] ≤ 1 per cycle #8
Sequence-dependent setup CP-SAT circuit / regular constraints, sequence variables #5, #33
No-overlap on shared team CP-SAT no_overlap on changeover intervals across machines #36
Mutex resources (Farcon ⊕ Dividella) CP-SAT Cumulative resource of capacity 1 #35
EVATON 2-batch / 3-week gap CP-SAT Forbidden-region / forbidden_assignments #49
Lag (prod→pack ≥ 4d, prod→label ≥ 3d) CP-SAT Precedence with min lag #46
Shelf-life storage CP-SAT Time-window on inventory intervals #48
Campaign coverage 6/9 mo MILP master Aggregated demand horizon #45
Tie-fairness MILP master Penalty on ` share[c] − fair_share
Schedule highest-score weeks first MILP master (soft) Lex-min on inverted scores #41
Glass machine selection by volume MILP master Eligibility set eligible(o) #31, #32

4. How the four solvers cooperate

4.1 Decomposition

                ┌──────────────────────────────┐
                │  Tier-1: Annual feasibility  │  LP / greedy
                │  Inputs:  total_qty, ratings │  Output: O* (confirmed orders)
                │  Time:    seconds            │
                └─────────────┬────────────────┘
                              │ O*, capacity envelope
                ┌─────────────▼────────────────┐
                │  Tier-2: Quarterly MILP      │  HiGHS / Gurobi via Pyomo
                │  Inputs:  O*, all hard cons. │  Output: x_pack, y_pack, qty_prod
                │  Time:    minutes            │  warm-started from prior cycle
                └─────────────┬────────────────┘
                              │ assignment locked, lines/weeks fixed
                ┌─────────────▼────────────────┐
                │  Tier-3: Weekly CP-SAT       │  OR-Tools
                │  Inputs:  Tier-2 assignment  │  Output: timed Gantt, changeovers
                │  Time:    seconds–minutes    │
                └─────────────┬────────────────┘
                              │ committed schedule
                ┌─────────────▼────────────────┐
                │  Tier-4: LNS repair          │  OR-Tools LNS
                │  Trigger: Photocells freeze  │  Output: patched local window
                │  Time:    < 1 minute         │  Disruption-Response Agent owns this
                └──────────────────────────────┘

                ┌──────────────────────────────┐
                │  Validation: DES simulator   │  Runs after Tier-3 and Tier-4
                │  Confirms KPIs on a stochastic replay before commit
                └──────────────────────────────┘

4.2 Why this split

  • MILP master handles linear, aggregated decisions (assignment, lot sizing, customer fairness) where dual variables are cheap and warm-starts work.
  • CP-SAT handles sequencing — no_overlap, sequence-dependent setup, forbidden regions — which are awkward to encode as MILP and where CP-SAT's propagation is faster.
  • LNS repairs after disruption without re-solving from scratch; the ALAS-style Disruption-Response Agent fixes a small destruction radius around the failure window.
  • DES simulator validates that a feasible schedule is also robust under throughput noise (Photocells variance) before SAP commit.

5. How LLM agents bridge the layers

The 6 specialist agents in PROPOSED_SOLUTION_ARCH.md each own a specific bridge:

Agent Bridge Inputs Outputs
Supervisor User intent → agent route NL request + context sub-agent invocation graph
Constraint-Elicitation NL → formal expr + Catalog row NL constraint, current catalog catalog patch (verified)
Schedule-Generation Catalog + data → solver call → plan catalog version, data snapshot, knobs Θ plan + KPIs + provenance
Infeasibility (OptiChat-style) Infeasible solver result → NL diagnosis IIS / minimum infeasible subsystem "These three constraints clash, and here's the cheapest one to relax"
What-If (OptiGuide-style) Parameter delta → re-solve + diff narration knob delta or hypothetical event counterfactual plan + KPI delta
Disruption-Response (ALAS-style) Telemetry event → LNS repair + narration Photocells freeze, ProdAction qty local repair patch
Explanation Plan numbers → audience-tuned narrative committed plan, persona shift view / order tracker / KPI dashboard

Verifier-in-the-loop sits between every agent and the catalog or SAP write:

Agent draft  ──►  Verifier
                  ├── Schema check        (JSON shape, types)
                  ├── Unit check          (units consistent with catalog)
                  ├── Feasibility check   (solver SAT on a frozen warm cache)
                  ├── Business-rule check (no contract violation, no SOX issue)
                  └── Audit-trail log     (who/what/why, immutable)
                  │
                  ▼
              Commit / reject

LLM hallucinations cannot reach SAP — every value is gated through the solver and the rules engine.


6. Bridging horizons (parent constraints, child warm-starts)

The same model is instantiated four times at four resolutions. Coherence is enforced by lifting parent decisions into child constraints and descending child observations into parent updates.

Annual (Tier-1)           ───► confirmed O*, capacity envelope
                                │
                                ▼ become parameters
Quarterly (Tier-2)         ───► assignment x_pack, y_pack, qty_prod
                                │
                                ▼ become bounds (warm-start + fix)
Weekly (Tier-3)            ───► sequence + changeover plan
                                │
                                ▼ become committed intervals
Real-time (Tier-4)         ◄───  telemetry says: window failed
                                │
                                ▲ rolls up: was Tier-2 over-optimistic?
Quarterly                   ◄───  if yes, re-rank in Tier-1 next cycle

This is a rolling-horizon design: every Monday morning the cycle re-fires, parameters update, last week's actuals replace last week's plan, and the four tiers re-converge.


7. Reference data flow — one full cycle

0. Cron (Mon 06:00) or user "run scheduler"
1. SAP Bridge MCP    : pull Planned Orders, Process Orders, BoM, mat-avail
2. Telemetry MCP     : pull last-week Photocells throughput + ProdAction batch sizes
3. Master-Data MCP   : load Constraint Catalog (current version)
4. Schedule-Generation Agent
   a. Tier-1 LP             — Solver MCP, mode=annual
   b. Tier-2 MILP            — Solver MCP, mode=quarterly, warm-start from last cycle
   c. Tier-3 CP-SAT          — Solver MCP, mode=weekly
   d. DES validate           — Simulator MCP, replays under Photocells variance
5. Verifier                  : schema + unit + feasibility + business rules
6. Explanation Agent
   a. Production view (Gantt by line × shift)         — req #13, #15
   b. Sales view    (order tracker)                   — req #14
   c. KPI dashboard (utilisation, fulfilment, OTIF)   — req #22
7. Approval queue (User Layer) — supervisor approves / amends
8. Audit MCP                 : version + diff vs last cycle
9. SAP Bridge MCP            : write Process Orders   — req #12
10. Live monitor             : Photocells events stream → Disruption-Response Agent
    a. On freeze ≥ τ minutes → Tier-4 LNS repair → re-verify → push to SAP

8. New / changing constraints — the change flow

The system is built so that changing a constraint is a data operation, not a deployment.

"From Q3 onward, the changeover team is 2 people instead of 1."
                   │
                   ▼
Constraint-Elicitation Agent
   - identifies C-036 (no-overlap of changeover team)
   - amends `team_capacity` parameter from 1 to 2 with effective_from = Q3
                   │
                   ▼
Verifier
   - schema OK, unit OK
   - feasibility check: does Q3 onwards still solve?  yes  →  pass
                       does Q1–Q2 still respect team_capacity = 1?  yes  →  pass
   - business-rule check: HR has signed off on the staffing change? gate on signed flag
                   │
                   ▼
Catalog version bump  v3 → v4   (diff:  C-036.team_capacity 1→2 from W27)
                   │
                   ▼
Re-solve trigger:   Tier-2 from W27 onward, warm-started from v3 plan
                   │
                   ▼
What-If Agent narrates:
   "v4 reduces total changeover hours by 14 % in Q3-Q4
    and frees 6 days of Marchesini GL capacity.
    Piramal monthly volume rises from 2.30M → 2.34M (still > band, see C-037)."
                   │
                   ▼
User approves       →  commit, audit, push to SAP
User rejects        →  catalog rolled back, audit logs the rejection rationale

Crucially: the LLM only writes catalog patches. The solver re-runs the formal model. The verifier independently re-checks. The user explicitly approves. None of those four can be skipped.


9. How this addresses each cluster of requirements

Requirement cluster Mechanism
Configurable scenarios (#1, #4) Knobs Θ are catalog rows; What-If Agent overlays deltas on Θ and re-solves.
Real-time monitoring + adjustment (#2, #3, #16) Telemetry MCP → Disruption-Response Agent → Tier-4 LNS repair.
Order-ranking algo (#4, #41) rating_score(o,Θ) is a configurable function inside Schedule-Generation.
Changeovers, maintenance, machine state (#5) Constraint catalog + CP-SAT sequencing.
Photocells / ProdAction inputs (#6) Telemetry MCP supplies throughput, batch size as parameters at solve time.
Deviation alerts (#7) Live monitor compares actual vs Tier-3 timeline; emits alerts to Disruption-Response.
Format-change rule, campaign cuts (#8, #33) MILP y_pack[m,f,w] ≤ 1 per cycle; CP-SAT sequence-dep setup.
Backup machines, configurable lines / SKUs (#9) Catalog eligible(o) set, editable.
Multi-objective trade-off (#10) Linear weighted sum on Θ; Pareto-front exploration via What-If.
Production + Packaging schedules (#11) Two-stage model with lag (req #46).
SAP integration (#12, #20–24) SAP Bridge MCP — read Planned Orders, write Process Orders, no double-entry.
Role-based UIs (#13–15, #22) Explanation Agent renders persona views from one underlying plan object.
52-week horizon, mixed cycle durations (#17, #18) Rolling-horizon Tier-1/2 absorbs both.
Capacity feasibility (#19) Tier-1 LP.
Manual breakdown declaration (#29) UI form → Telemetry MCP synthetic event → Disruption-Response.
Manual edit before SAP push (#30) Approval queue in User Layer; edits are constraint patches under verifier.
Glass-container machine rules (#31, #32) eligible(o) set + backup-line policy in catalog.
2025 PoC scope (#34) This dataset = 90.4 M ampoules, 1,824 demand lines.
Piramal band, Farcon ⊕ Dividella, no-overlap team (#35–37) Hard constraints in catalog; Verifier prevents commits that violate.
Order-indivisibility for orgs (#39) is_org flag → single-week constraint.
Tie-fair distribution (#40) Soft penalty on share deviation.
Production-side rules (#42–50) Production-tier MILP/CP block; EVATON forbidden regions; scrap parameter.

10. Verification & audit (non-negotiable)

Every committed plan and every constraint mutation is:

  1. Schema-validated against the catalog typing.
  2. Unit-checked (ampoules vs boxes, hours vs days, weeks vs months).
  3. Feasibility-checked by a real solver run on a frozen warm cache — not by the LLM.
  4. Business-rule-checked against contract / regulatory / SOX rules.
  5. Audit-logged (who, what, when, why, prior version) — immutable.

The LLM is never the source of truth on a number. The solver is.


11. Out of scope (this document)

  • Implementing any of the above. This is the approach, not the build plan.
  • Closing the gaps in MODEL_SCOPING.md §9 (changeover times, throughput, BoM, shelf life, due dates, etc.). Those are blocking inputs and remain client-side.
  • The PoC dataset is glass ampoules only (req #34) — extending to plastic ampoules / bottles / lyophillized is straightforward in this design (add lines, add formats, add catalog rows) but not in scope for the 2025 PoC.

12. Suggested first vertical slice (for a future build)

When implementation starts, the smallest end-to-end slice that exercises every layer:

  1. Data: Q1 2025 only, 3 customers (Piramal, CIS Farma, UK), 2ml + 5ml only, Marchesini GL + Farcon only.
  2. Catalog: 8 hard constraints (capacity, fulfilment, Piramal band, Farcon ⊕ Dividella, no-overlap team, prod→pack lag, format-once-per-cycle, glass-machine eligibility) + 1 soft (changeover penalty).
  3. Solver: Pyomo + HiGHS for Tier-2 only; skip Tier-1 (manual confirm), skip Tier-3 (use weekly aggregation), skip Tier-4 (no live disruption).
  4. Agents: only Schedule-Generation + Infeasibility + Explanation. Skip What-If, Disruption-Response.
  5. Output: a Gantt for Marchesini GL + Farcon over 13 weeks, KPI summary, infeasibility narration if catalog is unsatisfiable.

That slice is small enough to ship in a sprint and rich enough to validate the whole architecture pattern (catalog → solver → verifier → narration → audit) before scaling to the full problem.


Glossary / Abbreviations

Acronym Expansion / Meaning
ALAS An LLM-agent pattern for disruption-response that prefers local repair over full re-solve (referenced in PROPOSED_SOLUTION_ARCH.md).
API Active Pharmaceutical Ingredient — the substance produced upstream of packaging; drives the "one API per production week" rule (req #42).
BoM Bill of Materials — finished-product → semi-finished → API decomposition (req #26).
CP-SAT Constraint Programming-SATisfiability solver (Google OR-Tools); used for the sequencing layer (changeovers, no-overlap, sequence-dependent setup).
DES Discrete-Event Simulation — replays the schedule under throughput noise to validate robustness before SAP commit.
EVATON Specific semi-finished class with a 2-batch-at-a-time / ≥3-week-gap rule (req #49).
Fiori SAP's design system / UX framework for embedded enterprise UIs.
Gurobi / HiGHS Commercial / open-source MILP solvers.
IIS Irreducible Infeasible Subsystem — minimal set of conflicting constraints; output of the Infeasibility Agent.
KPI Key Performance Indicator.
LangGraph LangChain's stateful agent-orchestration framework (the supervisor + sub-agents in the architecture).
LLM Large Language Model.
LNS Large Neighborhood Search — metaheuristic for repairing a schedule by destroying and re-optimising a small window.
LP Linear Programming.
MCP Model Context Protocol — Anthropic's tool/service protocol; each backend service (Solver, Master-Data, SAP Bridge, Telemetry, Simulator, Audit) is exposed as an MCP server.
MILP Mixed-Integer Linear Programming.
MiniZinc Declarative constraint-modelling language (solver-agnostic); the catalog renders into MiniZinc fragments.
NL Natural Language.
OptiChat LLM-driven pattern for narrating infeasibility (IIS) to non-technical users.
OptiGuide Microsoft Research pattern for LLM-driven what-if analysis with parameter deltas + re-solve.
OR-Tools Google's open-source operations-research toolkit.
OTIF On Time In Full — the order-fulfilment KPI.
PoC Proof of Concept.
Pyomo Python algebraic modelling language for optimisation.
Q1 / Q2 / Q3 / Q4 Calendar quarters.
SAP The ERP system (DEMO's order-of-record); the SAP Bridge service reads Planned Orders and writes Process Orders.
SAT Boolean Satisfiability — the underlying solver class behind CP-SAT.
SKU Stock Keeping Unit (SAP Material Number).
SOX Sarbanes-Oxley Act — financial-controls compliance regime; constrains audit-trail and approval flows.
UI User Interface.
Unicef / Imres / ICRC / IDA / MSF Humanitarian organisations whose orders cannot be split (req #39).
VIP Very-Important order flag (weight 10,000 in the rating).
XYZ Three-axis customer-product rating: X = on-time/in-full grade (A–D), Y = order flexibility, Z = profitability tier.