- Having 2 days to prep labels and paperwork before crew arrives in the shop is super helpful. Organizing labels into piles that can be handed to crew saves a lot of time looking for labels and reference check lists
- During shop prep, have three places where crew can grab label or rack paperwork: new, in progress, and completed
- Crew grabs new bundle/cable labels/rack drawings, and info sheets from the "new" place. Crew returns completed tasks to the "completed place, so I can check them off. "In progress" place is for tasks that have been started but not completed
- like for not finishing something before end of day, or waiting on gear from the shops
- Crew grabs new bundle/cable labels/rack drawings, and info sheets from the "new" place. Crew returns completed tasks to the "completed place, so I can check them off. "In progress" place is for tasks that have been started but not completed
- paper folders for organizing drawings and labels
- equipment lists
- rack drawings
- check lists and bundle sheets
- tail labels
- medium labels
- big labels
- individual cable labels
Checklists in the left pocket, labels in the right pocket. Labels for bundles get paper stapled to their bundle sheet
- Tails/panels/stage boxes
- bundles
- loose cable
- Stek labels
- Rack drawings
- signal flows
- equipment lists and schedules
- Have a conversation with the design team ahead of time about what their expectations are for tech coverage
- If they want me to stay for the entirety of tech rehearsals, then I need an assistant to come in and handle notes in the morning. I may need their help to get that money approved with PM
- have a discussion about how often they want tech tables for preview rehearsals, and how that compares with my labor budget
- 2 @ 8hr days of pre-production
- 5 @ 8hr days of load in
- 2 @ 4hr days of QT
- 6 @ 8hr days of tech
- 7 @ 8hr days of preview notes/tech flips
- 2 @ 8hr days pre-strike
- 3 @ 8hr days strike
- Total Hours: 208
At an hourly rate of $35/hr, PSS fee should be at least $7,280 At an hourly rate of $40/hr, PSS fee should be at least $8,320
- 4 @ 8hr days of pre-production
- 5 @ 8hr days of shop prep
- 2 @ 4hr days of QT
- 1 @ 8hr days of band seating
- 6 @ 8hr days of tech
- 7 @ 8hr days of preview notes/tech flips
- 4 @ 8hr days pre-strike
- 5 @ 8hr days strike
- Total Hours: 264
At an hourly rate of $35/hr, PSS fee should be at least $9,240 At an hourly rate of $40/hr, PSS fee should be at least $10,560