Baseline established + critical path confirmed: Project start is 2026-01-02 with 125 days total duration. Critical path is T001 → T010 → T050 → T070 → T080 → T100 → T110 → T120 (Charter → Requirements → HW Design Freeze → EVT Build → FAT → Install → SAT → Qual).
Facilities is the current constraint (0% readiness): Facilities readiness is blocked and remains the most likely driver of install risk unless network/VLAN is cleared (or a compliant temporary workaround is approved).
Execution decision needed (controls churn): Controls readiness is 50%; we need to implement a FAT “release lock” (pin PLC/FW/HMI + IO map revision) to protect FAT evidence quality and reduce late integration surprises.