CNHI is modernizing its enterprise data capabilities by adopting Informatica Intelligent Data Management Cloud (IDMC) as the unified control plane for data integration, quality governance, and master data management. This greenfield implementation will:
- Eliminate manual ETL workloads for IBM mainframe and file-based systems (Week 23 production value)
- Establish data quality as a first-class operation with 5,000+ automated business rules across three prioritized waves
- Create authoritative master data for 35M+ beneficiaries and 25K+ provider records, enabling single-customer-view and compliance
- Catalog and govern 500+ data assets with end-to-end lineage and business glossary alignment
- Ensure 100% data residency in the Kingdom of Saudi Arabia via on-premises Secure Agents, with IDMC serving purely as a cloud-based SaaS control plane
This approach combines cloud agility with on-premises data sovereignty, delivering a secure, compliant, operationally transparent platform that CNHI teams will own and extend confidently.
| Challenge | Today | With IDMC |
|---|---|---|
| ETL Operations | Manual, error-prone, resource-intensive | Automated, resilient, governed |
| Data Quality | Ad-hoc validation, low visibility | 5,000+ rules, scorecards, real-time remediation |
| Master Data | Fragmented beneficiary/provider records | 35M+ golden records, single source of truth |
| Governance & Compliance | Scattered documentation, audit friction | Complete catalog, lineage, PDPL-ready |
| Future-Ready Data Ops | Limited agility, siloed systems | Extensible platform ready for AI/LLM pipelines |
Traditional Sequential Approach → Bottlenecks, months of waiting, delayed value
Sutherland's Parallel POD Approach → Three specialized teams working simultaneously
- POD 1 (CDI+CDQ): Data Integration & Quality — Weeks 1–48
- POD 2 (MDM): Master Data Management — Weeks 24–48 (parallel with POD 1)
- POD 3 (CDGC): Governance & Catalog — Weeks 11–48 (continuous)
Result: First production value in Week 23 (not Week 52+), and all four IDMC modules operational by Week 48.
| Dimension | Details |
|---|---|
| IDMC Modules | Cloud Data Integration (CDI), Cloud Data Quality (CDQ), Master Data Management (MDM), Data Governance & Catalog (CDGC) — All 4 in scope |
| Delivery Model | Wave-based incremental releases with 3 parallel PODs |
| Architecture | Hybrid: IDMC cloud orchestration + on-premises Secure Agents (100% data residency) |
| Source Systems | 8+ systems: IBM (CP4I), SQL Server, PostgreSQL, Oracle, SharePoint, APIs, file landing zones, and more |
| Data Volumes | 10 TB historical + ongoing weekly/monthly batches |
| Environments | Dev, Test, Prod (production with high availability) |
| Team Size | 12–13 Sutherland specialists + CNHI SMEs/stewards |
| Total Duration | 48 weeks (12 months) from contract to full handover |
| Production Go-Lives | 4 incremental releases: Week 23 (CDI/CDQ), Week 33, Week 41, Week 45 (MDM) |
| Milestone | Week | What's Delivered | Business Impact |
|---|---|---|---|
| Infrastructure Ready | 10 | Secure Agents operational, VPN/firewall, DW schema | Foundation for rapid build |
| Wave 1 Go-Live | 23 | IBM + Files automation, 1,000 DQ rules, 200 catalog entries | FIRST PRODUCTION VALUE: Manual ETL eliminated |
| Wave 2 Go-Live | 33 | Core databases (SQL Server, PostgreSQL, Oracle), 3,000 total DQ rules | 70% data coverage operational |
| Wave 3 Go-Live | 41 | Cloud/external sources (SharePoint, APIs), 5,000 total DQ rules, complete lineage | 100% CDI/CDQ/CDGC operational |
| MDM Go-Live | 45 | 35M+ golden records, stewardship workflows | Master data production-ready |
| Project Complete | 48 | Full hypercare, CNHI self-sufficient, all SLAs validated | Ready for independent operations |
All four IDMC modules are included in this engagement, sequenced across waves to deliver early value while building toward comprehensive governance.
- What: Ingest from 8+ source systems (IBM/CP4I, SQL Server, PostgreSQL, Oracle, SharePoint, APIs, files, etc.) into on-premises SQL Server DW
- Design Objectives:
- 50+ ETL/ELT mappings across three waves
- 10 TB historical migration in Wave 0–1
- Weekly/monthly batch processing with change-data-capture (CDC) foundation
- Heterogeneous file support (CSV, JSON, Parquet, DB backups)
- Error handling, quarantine patterns, reconciliation reports
- Key Deliverables:
- Dimensional data warehouse design (star schema)
- 50+ production mappings with documentation
- Batch scheduling framework
- Historical load reconciliation reports
- Incremental load patterns and restart logic
- Wave Delivery: Waves 1, 2, 3 (15–20 mappings per wave, refined in operations)
- What: Translate CNHI's business rules into enforceable, observable data quality checks
- Design Objectives:
- Up to 5,000 business rules across three prioritized waves (P0 → P1 → P2)
- Weekly profiling of 500+ tables
- DQ scorecards with pass-rate dashboards
- Violation tracking and remediation workflows
- Steward-facing task queues
- Approach: Rules are indicative targets subject to discovery. Wave 0 workshops will confirm actual rule count, prioritization, and implementation effort. Final rule volume may be adjusted per discovery outcome; success is measured by coverage of critical domains rather than rigid rule count.
- Key Deliverables:
- 5,000 rules (estimate) implemented across waves, with actual scope confirmed post-discovery
- DQ scorecards (target ≥90% pass rate Wave 1, ≥95% Wave 3)
- Violation dashboards and remediation trackers
- Steward training and workflow documentation
- Wave Delivery: Waves 1, 2, 3 (priority-based rule activation)
- What: Create and operate authoritative golden records for beneficiaries and providers
- Design Objectives:
- Match rules reflecting CNHI's data realities (noisy identifiers, multilingual names, variations)
- Survivorship logic prioritizing authoritative sources per attribute
- Stewardship workflows for complex matches requiring human judgment
- Sample tuning (Wave 2, ~5M records) → full-scale loads (Wave 3)
- Golden record creation with audit trails
- Approach: Match coverage targets are qualitative (≥98% matching confidence on sample data) rather than rigid precision/recall commitments, allowing refinement during Waves 2–3. Success is measured by operational readiness and steward confidence in golden records.
- Key Deliverables:
- MDM match rules and survivorship hierarchies
- 35M+ beneficiary golden records (wave 3–4 load)
- 25K+ provider golden records
- Stewardship workflows and approval processes
- Sample load validation report (Wave 2)
- Full-scale load reconciliation (Wave 3)
- Wave Delivery: Waves 2, 3, 4 (sample → full-scale → production)
- What: Inventory, catalog, classify, and trace all data assets and lineage
- Design Objectives:
- 500+ tables cataloged (estimate, subject to discovery)
- Native scanners (SQL Server, SharePoint) + integration-derived metadata for unavailable scanners
- End-to-end lineage from source → Secure Agent transformations → DW
- Business glossary import and mapping to physical assets
- Data classification (PII, confidential, retention rules)
- Weekly metadata scans and updates
- Approach: Catalog scope is discovery-driven. The goal is completeness of visibility rather than rigid table count; final scope will be confirmed during Wave 0 source profiling.
- Key Deliverables:
- 500+ tables in catalog (indicative, subject to discovery)
- Lineage visualization end-to-end
- Business glossary terms mapped to assets
- Data classification tags
- Governance workflows and stewardship assignments
- Weekly metadata scan automation
- Wave Delivery: Waves 1, 2, 3 (incremental catalog expansion)
Eight or more source systems will be integrated across three waves. Priorities can be adjusted during Wave 0 based on CNHI's evolving business needs.
| # | Source System | Type | Integration Method | Default Priority | Default Wave | Flexibility |
|---|---|---|---|---|---|---|
| 1 | IBM (DB2, AS/400) | Mainframe | Via CP4I | 🔴 Critical | Wave 1 | Fixed (manual ETL elimination) |
| 2 | File Landing Zones (CSV, JSON, Parquet) | Files | SFTP/shared folder connector | 🔴 Critical | Wave 1 | Fixed (manual ETL elimination) |
| 3 | SQL Server Data Mart | RDBMS | JDBC | 🟡 High | Wave 1 | Can move to Wave 2 if needed |
| 4 | PostgreSQL | RDBMS | JDBC | 🟡 High | Wave 2 | Flexible—can swap with Oracle |
| 5 | Oracle Database | RDBMS | JDBC | 🟡 High | Wave 2 | Flexible—can move to Wave 3 |
| 6 | SharePoint Online | Cloud SaaS | OAuth 2.0 connector | 🟠 Medium | Wave 3 | Flexible—can accelerate to Wave 2 |
| 7 | REST/SOAP APIs | External | REST/SOAP connectors | 🟠 Medium | Wave 3 | Flexible—can accelerate if business urgent |
| 8 | Oracle ERP | ERP | JDBC | 🔵 Low/Deferred | Future | Can move into Wave 2/3 if access available |
| + | Additional emerging sources (MongoDB, email, etc.) | Varied | TBD per connector | 🔵 Backlog | Future | Added as needed in operations phase |
Flexibility Model: During Wave 0, CNHI can re-order Wave 2 and Wave 3 sources without jeopardizing delivery, provided core Wave 1 sources (IBM, Files) remain fixed. Sutherland will support this agility via sprint-based scope control and transparent dependency tracking.
| Component | Specification | Purpose | CNHI vs. Sutherland |
|---|---|---|---|
| Secure Agent VMs (Prod) | 2 VMs @ 16 vCPU, 64 GB RAM, 1 TB SSD each (CDI/CDQ group + MDM group) | High-availability on-premises execution | CNHI provisions; Sutherland installs/configures |
| Secure Agent VMs (Non-Prod) | 2 VMs @ 8–16 vCPU, 32–64 GB RAM, 500 GB SSD (Dev + Test) | Right-sized development/testing | CNHI provisions; Sutherland installs/configures |
| Agent Groups | DEV, TEST, PROD-CDI-CDQ (POD 1), PROD-MDM (POD 2) | Workload isolation & environment separation | Sutherland designs & configures |
| Network Connectivity | IPSec site-to-site VPN (AES-256) + TLS 1.2+ HTTPS (port 443) — VPN preferred; internet egress fallback | Secure outbound tunnel from data center → IDMC cloud | CNHI network + Informatica; Sutherland validates |
| SQL Server Data Warehouse | 15–20 TB capacity, TDE encryption | On-premises target repository | CNHI provisions & maintains; Sutherland designs schema & tunes performance |
| OS & Patching | Windows Server 2022 (preferred) or RHEL Linux (where Informatica-confirmed compatible) | Secure Agent host OS | CNHI provides; Sutherland validates compatibility in Wave 0 |
| Monitoring & Alerting | IDMC native monitoring + local OS metrics (CPU, memory, network) | Operational visibility | Sutherland configures dashboards; CNHI operates |
Key Assumptions:
- Informatica will confirm in writing (Wave 0 dependency) that all required CDI/CDQ/MDM/CDGC connectors and modules are fully supported on Windows Server 2022 for the Saudi Arabia regional tenant.
- VPN tunnel infrastructure (IPSec endpoints, key management) is CNHI's responsibility; Sutherland assists with validation and monitoring configuration.
- SQL Server DW hardware, patching, and availability are CNHI-owned; Sutherland provides performance tuning support (indexing, partitioning, query optimization, maintenance job configuration).
| Metric | Design Objective | Wave Achievement | Notes |
|---|---|---|---|
| Nightly Batch Window | ≤3 hours for full daily processing (CDC + quality checks) | Target by Wave 1 go-live | Subject to source availability and network latency; will be jointly tuned during Week 23 cutover and Wave 2 expansion |
| DQ Rule Pass Rate | Wave 1: ≥90% | Wave 1: ≥90%; Wave 2: ≥92%; Wave 3: ≥95% | Targets are design objectives, not contractual commitments; actual rates depend on upstream data remediation (CNHI responsibility) |
| MDM Match Coverage | ≥98% of records matched with ≥90% confidence | Validated in Wave 2 sample (5M records), refined by Wave 3 full load | "Match coverage" = % of input records successfully matched to a golden record or correctly identified as new; precision/recall tuned during Wave 2 |
| Catalog Completeness | 500+ assets cataloged with lineage | Phased: 200 in Wave 1, 350 by Wave 2, 500+ by Wave 3 | Subject to actual source inventory discovered in Wave 0 |
| Agent Availability | 99.5% uptime (high-availability configuration, 2 agents per prod group) | Measured across nightly batch windows | Excludes CNHI-side network outages or source system unavailability |
SLA Philosophy: These metrics are design targets and operational objectives that Sutherland and CNHI will jointly tune during the project. Success is measured by continuous improvement and operational readiness, not rigid contractual pass-fail thresholds. Any variance (e.g., 92% vs. 95% DQ pass rate, or batch window 3.5 vs. 3 hours) will be addressed through optimization sprints and root-cause analysis, not penalties.
| Activity | Why Out of Scope | CNHI Ownership |
|---|---|---|
| Source System Modifications | Applications own their data contracts; Sutherland integrates as-is | CNHI decides if upstream systems need changes to support IDMC pipelines |
| Data Remediation at Source | DQ identifies issues; fixing them upstream is a business/app decision | CNHI owns root-cause analysis and remediation in source systems |
| Enterprise Governance Policies | Organization-level data governance, data ownership, stewardship models | CNHI defines; Sutherland enforces within IDMC configuration |
| BI Tool Development | Power BI, Tableau, or other reporting layer | CNHI builds reports on DW; Sutherland delivers DW with optimized schemas |
| SQL Server DW Provisioning & Patching | Infrastructure is CNHI's responsibility | CNHI provisions, patches, backs up; Sutherland tunes performance and design |
| Change Management / User Adoption | Organizational change is external to technical delivery | CNHI runs adoption programs; Sutherland provides training |
| LLM / GenAI Model Training | AI engineering is adjacent to data pipelines | Sutherland ensures data lineage and quality for AI inputs; CNHI builds models |
| Post-Wave-5 Managed Services (AMS) | Base engagement covers delivery + hypercare only | Optional post-project AMS is separate engagement (see Section 10: Engagement Terms) |
Core Principle: IDMC is a SaaS orchestration and governance layer (cloud-based). All data processing, transformation, and quality checks run on on-premises Secure Agents. Data never leaves CNHI's network boundary unless explicitly authorized and masked.
┌─────────────────────────────────────────────────────────────────┐
│ INFORMATICA IDMC (Cloud) │
│ • Design Studio (pipeline authoring) │
│ • Job Scheduler & Orchestration │
│ • Monitoring, Logs, Lineage │
│ • Governance, Catalog, Glossary │
│ • (Saudi-hosted GCP instance for PDPL compliance) │
└──────────────────────────┬──────────────────────────────────────┘
│ (Outbound-initiated TLS 1.2+ HTTPS)
│ (No inbound ports; metadata only)
│
┌──────────────────────────┴──────────────────────────────────────┐
│ CNHI DATA CENTER (On-Premises) │
├─────────────────────────────────────────────────────────────────┤
│ │
│ ┌────────────────────────────────────────────────────────┐ │
│ │ Secure Agent Groups (VMs, Windows Server 2022) │ │
│ ├────────────────────────────────────────────────────────┤ │
│ │ POD 1: CDI/CDQ Group (2 agents HA) │ │
│ │ ├─ Read from IBM, Files, SQL Server, etc. │ │
│ │ ├─ Apply transformations, DQ rules │ │
│ │ ├─ Load SQL Server DW │ │
│ │ └─ Orchestrated by IDMC cloud │ │
│ │ │ │
│ │ POD 2: MDM Group (2 agents HA) │ │
│ │ ├─ Read from DW (integrated data) │ │
│ │ ├─ Execute match/merge logic │ │
│ │ ├─ Create/update golden records │ │
│ │ └─ Orchestrated by IDMC cloud │ │
│ └────────────────────────────────────────────────────────┘ │
│ │
│ ┌────────────────────────────────────────────────────────┐ │
│ │ Source Systems (Unchanged) │ │
│ ├────────────────────────────────────────────────────────┤ │
│ │ • IBM DB2, AS/400 (via CP4I) │ │
│ │ • SQL Server, PostgreSQL, Oracle (JDBC) │ │
│ │ • SharePoint, APIs (OAuth, REST) │ │
│ │ • File Landing Zones (SFTP, SMB) │ │
│ │ • Email, MongoDB, custom connectors (as needed) │ │
│ └────────────────────────────────────────────────────────┘ │
│ │
│ ┌────────────────────────────────────────────────────────┐ │
│ │ SQL Server Data Warehouse (Target) │ │
│ ├────────────────────────────────────────────────────────┤ │
│ │ • Dimensional schema (star: facts + dimensions) │ │
│ │ • 15–20 TB capacity, TDE encryption │ │
│ │ • Optimized for analytics (indexes, partitioning) │ │
│ │ • Performance-tuned by Sutherland │ │
│ └────────────────────────────────────────────────────────┘ │
│ │
└─────────────────────────────────────────────────────────────────┘
Option 1: IPSec Site-to-Site VPN (Recommended)
- How: Dedicated encrypted tunnel from CNHI data center to Informatica's Saudi GCP instance
- Protocol: IPSec with AES-256 encryption, IKEv2
- Benefits:
- Deterministic latency and throughput
- No public IP exposure
- Double encryption (VPN + TLS)
- Easier traffic inspection and monitoring
- Supports future multi-tenancy scenarios
- Effort: CNHI network team + Informatica provision endpoints; Sutherland validates configuration and performance
Option 2: Outbound HTTPS (Internet Egress)
- How: Secure Agents initiate TLS 1.2+ HTTPS connections on port 443 to Informatica cloud endpoints
- Benefits:
- Simple, immediate deployment (no VPN provisioning)
- Works with standard corporate firewalls
- Lower infrastructure overhead
- Trade-off: Latency variability, requires public IP whitelisting
- Fallback: Recommended only if VPN unavailable
CNHI's Choice in Wave 0: Sutherland will validate both options and recommend VPN as the primary path based on security best practices and latency requirements. Final selection will be jointly made during infrastructure workshops.
| Scenario | What Flows | Encryption | Masking |
|---|---|---|---|
| Normal Operation | Commands, job status, logs, metadata, counters | IPSec + TLS 1.2+ | Not needed (metadata only) |
| Administrative Preview | Sample records for troubleshooting (rare) | IPSec + TLS 1.2+ | PII masked by policy |
| Non-Production Testing | Full copies of non-sensitive data (Dev/Test) | IPSec + TLS 1.2+ | All PII masked |
| Compliance Audit | Lineage reports, lineage graphs (PDPL/audit) | IPSec + TLS 1.2+ | Aggregated; no individual records |
Golden Rule: Raw beneficiary or provider data never traverses CNHI's network boundary in unencrypted or unmasked form.
Each production POD runs two Secure Agents in active-active configuration:
- Agent 1: Primary execution, handles 50% of workload
- Agent 2: Standby, assumes full workload if Agent 1 fails
- Failover: Automatic; transparent to IDMC orchestration
- Data Consistency: Shared state via IDMC cloud coordination
Capacity Management:
- Wave 1: 2 agents per group sufficient for initial data loads and batch processing
- Wave 2–3: If batch windows exceed SLA or job queues grow, add third agent (elastic scaling)
- Operations: CNHI can add/remove agents per resource availability and workload
- Dev & Test: Single agent per environment initially; can scale if needed
- Promotion Discipline: Same configuration across Dev → Test → Prod ensures reliability
Secure Agent OS Preference:
- Windows Server 2022 (preferred) — aligns with CNHI's Microsoft-centric operations
- Red Hat Enterprise Linux 8.x (supported alternative) — where CNHI prefers Linux
Wave 0 Dependency: Informatica will provide written confirmation that all required connectors and modules (CDI, CDQ, MDM, CDGC) are fully supported on Windows Server 2022 for the Saudi Arabia region, with no feature loss vs. Linux. If variance exists, Sutherland and CNHI will decide on a case-by-case basis.
Waves deliver incremental business value and reduce risk. Parallel PODs prevent bottlenecks and accelerate time-to-value.
| Aspect | Traditional Sequential | Sutherland Wave + POD Model |
|---|---|---|
| CDI Completion | All sources ready, then start CDQ | POD 1: Waves 1–3 concurrent with POD 2 MDM work |
| Time to First Value | 52+ weeks (after all modules complete) | Week 23 (Wave 1 go-live: manual ETL automated) |
| Risk | Late discovery = cascade delays | Early wins reduce scope uncertainty |
| Team Utilization | Sequential = idle periods | Parallel = continuous momentum |
| Change Agility | Hard to re-prioritize sources | Sprint-based, re-prioritize week-to-week |
| Wave | Weeks | Focus | PODs Active | Production Go-Live | Key Business Value |
|---|---|---|---|---|---|
| Wave 0 | 1–10 | Foundation, discovery, DW design, infrastructure | All (setup) | — | Solid foundation, detailed requirements |
| Wave 1 | 11–23 | IBM + Files automation, 1K DQ rules, catalog foundation | POD 1, POD 3 | Week 23 | Manual ETL eliminated |
| Wave 2 | 24–33 | Core databases, 2K DQ rules, MDM sample load | POD 1, POD 2, POD 3 | Week 33 | 70% data coverage; MDM tuning underway |
| Wave 3 | 34–41 | Cloud/external sources, 2K final DQ rules, full MDM load | POD 1, POD 2, POD 3 | Week 41 | 100% CDI/CDQ/CDGC; golden records ready |
| Wave 4 | 42–45 | MDM production deployment | POD 2 | Week 45 | Master data operational |
| Wave 5 | 46–48 | Regression testing, optimization, handover | All | Week 48 | CNHI self-sufficient |
Objective: Build solid infrastructure, detailed discovery, data warehouse design, and technical blueprints across all four IDMC modules.
| Category | Activities | Duration | Deliverable |
|---|---|---|---|
| Discovery & Requirements | Source system profiling (8+ sources), data quality rule inventory (estimate 5K), governance glossary assembly, dimensional modeling workshops | Weeks 1–3 | Discovery Summary Report, Source Inventory Spreadsheet, DQ Rule Priorities (P0/P1/P2) |
| DW Design | Dimensional star-schema design, physical schema (tables, columns, keys), indexing strategy, partitioning approach | Weeks 2–4 | Data Warehouse Design Document, ERDs, Data Dictionary |
| Technical Blueprints | CDI approach per POD 1, CDQ approach per POD 1, MDM match/survivorship per POD 2, CDGC catalog & lineage per POD 3 | Weeks 3–5 | Technical Architecture Document (4 modules), proof-of-concept demo (sample mapping) |
| Infrastructure Setup | VM provisioning (8 VMs total: 4 Prod, 2 Test, 2 Dev), OS installation, Secure Agent installation, firewall whitelisting, optional VPN tunnel provisioning | Weeks 1–8 | Infrastructure As-Built Document, Network Topology Diagram, Agent Health Checklist |
| Governance & Access | Service account creation (SQL Server, SharePoint, APIs, file shares), IDMC tenant access roles defined, network security review, monitoring setup | Weeks 3–8 | Service Account Inventory, Access Control Matrix, Monitoring Dashboard |
| Deliverable | Description | Acceptance By |
|---|---|---|
| Discovery Summary Report | All 8+ sources documented: schemas, volumes, growth rates, known data issues, business rules, integration constraints | CNHI IT Director |
| Data Warehouse Design Document | Dimensional model (star schema), physical schema, data dictionary, ETL framework, index/partition strategy | CNHI BAs + Steering Committee |
| DQ Rule Catalog | 5,000 rules estimated, prioritized by wave (Wave 1: ~1K, Wave 2: ~2K, Wave 3: ~2K), with business context and validation logic | CNHI SMEs |
| MDM Requirements Document | Match criteria per domain, survivorship rules, stewardship workflows, sample match strategy | CNHI Data Stewards |
| Technical Architecture Document | Module-by-module design (CDI, CDQ, MDM, CDGC), agent group strategy, security posture, performance targets | CNHI Architecture Review Board |
| Infrastructure As-Built | VMs, agent groups, network topology, VPN config (if chosen), monitoring setup; agents ✅ operational and connected | CNHI IT & Security |
| Source Priority Confirmation | Final wave assignments per source (Wave 1 fixed: IBM + Files; Waves 2–3 flexible per CNHI business needs) | CNHI Executive Sponsor |
- ✅ All 8 Secure Agents operational and heartbeat confirmed with IDMC
- ✅ VPN tunnel stable (if chosen) with latency < 50 ms
- ✅ SQL Server DW database created with base schema
- ✅ All 4 IDMC module blueprints approved
- ✅ Source priorities finalized (IBM + Files in Wave 1, others re-orderable in Waves 2–3)
- ✅ DQ rule count finalized and prioritized (actual vs. 5K estimate confirmed)
- ✅ All POD teams mobilized and ready to sprint
Objective: Deliver first production value by automating CNHI's most painful manual ETL workloads (IBM mainframe and file-based loads).
🚀 Production Go-Live: Week 23
| Component | What | Business Value |
|---|---|---|
| IBM Sources | IBM DB2/AS/400 via Cloud Pak for Integration; ~2–3 TB historical | Eliminate mainframe manual extracts |
| File Sources | CSV, JSON, Parquet, DB backups from SFTP/shared folders; ~1–2 TB historical | Automate file processing |
| SQL Server | Existing data mart; supporting source | Integrated into DW |
| DQ Rules | 1,000 P0 rules (highest priority: identity, mandatory fields, type/range checks) | Data quality at source |
| Catalog | 200 tables cataloged with basic lineage | Data discovery enabled |
| Weeks | POD 1 (CDI+CDQ) | POD 2 (MDM) | POD 3 (CDGC) |
|---|---|---|---|
| 11–14 | CP4I connectivity, 5 IBM mappings, 500 DQ rules, SQL testing | MDM requirements workshops | Catalog IBM, File sources |
| 15–18 | File automation, 10 file mappings, 500 DQ rules, SQL integration | MDM requirements workshops | Catalog SQL Server |
| 19–20 | Hardening, testing all pipelines, error handling | — | Lineage validation |
| 21–22 | Mini-UAT (2 weeks): CNHI UAT team executes test cases | — | UAT support |
| 23 | PRODUCTION GO-LIVE | — | Catalog live, lineage operational |
Bi-weekly Sprint Demos: Weeks 12, 14, 16, 18, 20 to CNHI stakeholders
| Deliverable | Acceptance Criteria |
|---|---|
| 15–20 ETL Mappings | IBM, Files, SQL Server → DW; tested; documented; scheduled |
| 4–5 TB Historical Data Loaded | Reconciliation report shows 100% match |
| 1,000 DQ Rules Live | Pass rate ≥90% on Wave 1 data; violations tracked in detail |
| 200 Tables Cataloged | Searchable in IDMC catalog; business users can discover assets |
| Production Go-Live Report | First nightly batch successful; SLAs monitored |
| UAT Sign-Off | CNHI business users formally accept Wave 1 solution |
- ✅ 15–20 mappings operational and scheduled nightly
- ✅ 4–5 TB historical data loaded (100% reconciliation)
- ✅ 1,000 DQ rules live (≥90% pass rate)
- ✅ 200 tables cataloged with lineage
- ✅ UAT sign-off received from CNHI
- ✅ PRODUCTION GO-LIVE: Week 23 ← First Business Value Delivered
Objective: Add PostgreSQL and Oracle; expand DQ rules; begin MDM hands-on development.
🚀 Production Go-Live: Week 33 | Cumulative: 70% Data Coverage
| Component | What | Business Value |
|---|---|---|
| CDI — Databases | PostgreSQL, Oracle → DW; ~2–3 TB historical | Expand data integration coverage |
| CDQ — Expanded Rules | 2,000 P1 rules (business semantics: standardization, formatting, cross-field checks) | Broader quality coverage |
| CDGC — Expanded Catalog | 150 additional tables (350 total); extended lineage | Enhanced data discovery |
| MDM — Sample Load | 5M beneficiary records sample; match tuning; algorithm validation | MDM foundation (parallel with POD 1) |
| Weeks | POD 1 (CDI+CDQ) | POD 2 (MDM) | POD 3 (CDGC) |
|---|---|---|---|
| 24–27 | PostgreSQL, Oracle design; 10 mappings started | 5M sample load initiated; match rules tuned | Catalog additional sources |
| 28–30 | 2,000 DQ rules implemented; testing | Match threshold tuning; precision/recall validation | Lineage expansion |
| 31 | Error handling hardening | — | UAT preparation |
| 32–33 | Mini-UAT (2 weeks) | — | UAT support |
| 33 | PRODUCTION GO-LIVE | Sample load validated | Catalog live |
| Deliverable | Acceptance Criteria |
|---|---|
| 20 Additional Mappings | PostgreSQL, Oracle → DW (35 total mappings) |
| 2–3 TB Additional Data | Reconciliation 100% |
| 2,000 Additional DQ Rules | Pass rate ≥92% (3,000 total rules) |
| 350 Total Tables Cataloged | Business users utilizing catalog for discovery |
| 5M MDM Sample Load | Match algorithm validated; coverage ≥95% |
| UAT Sign-Off | CNHI accepts Wave 2 |
- ✅ 35 total mappings operational
- ✅ 6–8 TB total data loaded
- ✅ 3,000 total DQ rules (≥92% pass rate)
- ✅ 350 tables cataloged
- ✅ 5M MDM sample successful (match coverage ≥95%)
- ✅ PRODUCTION GO-LIVE: Week 33
Objective: Complete all CDI/CDQ/CDGC modules; execute full-scale MDM load.
🚀 Production Go-Live: Week 41 | Cumulative: 100% CDI/CDQ/CDGC
| Component | What | Business Value |
|---|---|---|
| CDI — Cloud/External | SharePoint, APIs, additional sources; ~2–3 TB | Complete data integration |
| CDQ — Complete Rules | 2,000 P2 rules (cross-record, referential, extended checks); 5,000 total | Full quality coverage |
| CDGC — Complete Catalog | 150 additional tables (500 total); full end-to-end lineage | Complete governance |
| MDM — Full Load | 35M beneficiary + 25K provider full load; golden record creation | Complete MDM operational |
| Weeks | POD 1 (CDI+CDQ) | POD 2 (MDM) | POD 3 (CDGC) |
|---|---|---|---|
| 34–36 | SharePoint OAuth; API connectors; 15 final mappings | Full 35M load initiated | Catalog completion |
| 37–39 | 2,000 final DQ rules; extended checks | Golden record tuning; stewardship workflow testing | Lineage finalization |
| 40 | Hardening and testing | — | Final validation |
| 41 | PRODUCTION GO-LIVE | Full load completed, ready for UAT | Catalog live |
| Deliverable | Acceptance Criteria |
|---|---|
| 15 Final Mappings | All 50+ mappings operational |
| 10 TB Total Historical Data | Complete data loaded and reconciled |
| 5,000 Total DQ Rules | Pass rate ≥95% overall |
| 500 Total Tables Cataloged | Complete catalog |
| Complete Lineage | End-to-end lineage visible for compliance/impact analysis |
| 35M+ Golden Records (MDM) | Ready for production UAT |
| UAT Sign-Off (CDI+CDQ+CDGC) | CNHI accepts Wave 3 |
- ✅ All 50+ mappings operational
- ✅ All 10 TB data loaded
- ✅ All 5,000 DQ rules live (≥95% pass rate)
- ✅ All 500 tables cataloged
- ✅ Complete lineage documented
- ✅ 35M+ golden records created
- ✅ PRODUCTION GO-LIVE: Week 41
Objective: Cutover from sample to full operational MDM.
🚀 MDM Production Go-Live: Week 45
| Week | Activity | Owner |
|---|---|---|
| 42 | Golden record validation with CNHI SMEs; workflow testing; steward training begins | POD 2 + CNHI stewards |
| 43–44 | MDM UAT (2 weeks): Stewards test conflict resolution, workflow, approval processes | POD 2 + CNHI stewards |
| 45 | MDM Production Go-Live: Golden records operational; stewardship live | POD 2 |
| Deliverable | Acceptance Criteria |
|---|---|
| 35M+ Beneficiary Golden Records | ≥98% match coverage; production-ready |
| 25K+ Provider Golden Records | ≥98% match coverage; production-ready |
| MDM Hub Operational | Stewardship workflows live |
| Stewards Trained | Stewards can resolve conflicts independently |
| UAT Sign-Off (MDM) | CNHI stewards accept MDM solution |
- ✅ 35M+ beneficiary records (≥98% coverage)
- ✅ 25K+ provider records (≥98% coverage)
- ✅ MDM Hub operational
- ✅ Stewards trained
- ✅ MDM PRODUCTION GO-LIVE: Week 45
Objective: End-to-end testing, optimization, operational readiness, project closure.
✅ Complete Solution Operational: Week 48
| Week | Activity | Owner |
|---|---|---|
| 46 | End-to-end regression tests; performance tuning; admin training | All PODs |
| 47 | User training finalized; runbooks reviewed; final optimization | All PODs |
| 48 | Hypercare kickoff; operations handover; project closure | Sutherland + CNHI |
| Deliverable | Acceptance Criteria |
|---|---|
| Regression Test Report | All end-to-end tests passed |
| Performance Report | Batch window ≤3 hours; SLAs met |
| Runbooks | CNHI operations can run platform independently |
| Training Records | Admin + user training completed; sign-offs received |
| Hypercare Log | No critical open issues; lessons learned documented |
| Project Closure Report | Steering committee formal approval |
- ✅ End-to-end regression complete
- ✅ Performance validated (batch window ≤3 hours)
- ✅ CNHI operations team certified
- ✅ 3-week hypercare complete
- ✅ PROJECT COMPLETE: Week 48
Sutherland commits a dedicated core team of 12–13 specialists, organized into three parallel PODs with shared leadership services.
┌─────────────────────────────────────────────────────────┐
│ SUTHERLAND DELIVERY LEADERSHIP (Shared) │
├─────────────────────────────────────────────────────────┤
│ • Solution Architect (1) — overall design, non-functional requirements |
│ • Project Coordinator (1) — sprint planning, risk/dependency tracking |
│ • Infrastructure Engineer (1) — VMs, agents, connectivity, monitoring |
│ • Technical Writer (1) — runbooks, training, documentation |
└─────────────────────────────────────────────────────────┘
│
┌──────────────────┼──────────────────┐
│ │ │
┌────▼─────┐ ┌────▼─────┐ ┌────▼─────┐
│ POD 1 │ │ POD 2 │ │ POD 3 │
│ CDI+CDQ │ │ MDM │ │ CDGC │
└──────────┘ └──────────┘ └──────────┘
(8–9 people) (4–5 people) (2–3 people)
Charter: Design and build all ETL pipelines, data quality rules, and operational frameworks.
| Role | FTE | Responsibilities |
|---|---|---|
| CDI/CDQ Technical Lead | 1.0 | Designs integration patterns; reviews code; mentors developers; owns performance tuning |
| Integration Developers | 3.0 | Build and maintain mappings; design error handling; implement CDC frameworks |
| Data Quality Specialists | 2.0 | Translate business rules into IDMC tasks; design scorecards; build remediation workflows |
| Catalog Specialist | 1.0 | (Shared with POD 3) Captures metadata from CDI pipelines; maintains lineage |
| QA Engineer | 1.0 | Functional test coverage; UAT coordination; error handling validation |
Engagement Duration: Weeks 1–48 (full program)
Peak Workload: Waves 1–3 (active development); Wave 4 (support); Wave 5 (regression/optimization)
Charter: Design and implement match rules, survivorship logic, and stewardship workflows.
| Role | FTE | Responsibilities |
|---|---|---|
| MDM Technical Lead | 1.0 | Designs match algorithms; configures survivorship rules; performance tunes; owns hub operations |
| MDM Specialists | 2.0 | Configure match algorithms; tune thresholds; design golden record structures; validate sample loads |
| QA Engineer | 1.0 | Validates match coverage; tests stewardship workflows; UAT coordination |
Engagement Duration: Weeks 1–10 (planning), Weeks 24–48 (active development + go-live)
Peak Workload: Waves 2–4 (sample tuning → full load → production deployment)
Charter: Manage cataloging, metadata harvesting, lineage, and governance workflows.
| Role | FTE | Responsibilities |
|---|---|---|
| Catalog & Governance Lead | 1.0 | Designs catalog strategy; schedules scanners; owns lineage; maintains governance policies |
| Catalog/Metadata Specialist | 1.0 | (Shared with POD 1) Harvests metadata; maps glossary terms; validates lineage |
Engagement Duration: Weeks 1–48 (continuous)
Peak Workload: Waves 1–3 (catalog expansion); Waves 4–5 (optimization)
| Role | FTE | Responsibilities |
|---|---|---|
| Solution Architect | 1.0 | Oversees non-functional requirements (security, availability, performance); reviews key designs; resolves architecture questions; escalation point |
| Project Coordinator | 1.0 | Sprint planning; status reporting; dependency tracking; risk management; steering committee coordination |
| Infrastructure Engineer | 1.0 | VM provisioning, OS hardening, agent installation, network troubleshooting, monitoring setup |
| Technical Writer | 1.0 | Runbooks, configuration guides, training materials, lessons learned documentation |
| Cadence | Activity | Participants |
|---|---|---|
| Weekly | Cross-POD sync (1 hour) | All POD leads + shared leadership |
| Bi-Weekly | Sprint demos (1.5 hours) | All Sutherland + CNHI stakeholders |
| Bi-Weekly | Steering committee (1 hour) | Leadership + CNHI executive sponsor |
| Weekly | Dependency tracking review | Project coordinator + POD leads |
| Per-Demand | Architecture reviews | Solution architect + relevant POD |
| CNHI Role | Time Commitment | Key Responsibilities |
|---|---|---|
| Executive Sponsor | 2–3 hrs/week | Prioritize decisions; remove roadblocks |
| IT Director | 3–5 hrs/week | Infrastructure provisioning; security approvals |
| Business SMEs | 5–10 hrs/week | Define DQ rules; validate mappings; prioritize sources |
| Data Stewards | 5–10 hrs/week (Wave 0–2), 15–20 hrs/week (Wave 3–4) | Own DQ remediation; validate MDM golden records; run stewardship workflows |
| DBAs | 3–5 hrs/week | DW design review; performance tuning; index maintenance |
| Network & Security | 5–10 hrs/week (Wave 0) | VPN provisioning; firewall rules; security validation |
| UAT Teams | 10–20 hrs/week (per wave) | Execute test cases; sign-off on deliverables |
Week 1 10 20 30 40 48
│ │ │ │ │ │
Wave 0: ├─────────┤ (Foundation)
│
Wave 1: │ ├─────────────────────┤ (IBM + Files → Prod Week 23)
│
Wave 2: │ │ ├──────────────────┤ (DBs → Prod Week 33)
│
Wave 3: │ │ │ ├────────┤ (Cloud → Prod Week 41)
│
Wave 4: │ │ │ │ ├──┤ (MDM → Prod Week 45)
│
Wave 5: │ │ │ │ │ ├─┤ (Handover → Week 48)
│
POD 1: ├─────────────────────────────────────────────────────────────┤ (CDI+CDQ continuous)
│
POD 2: ├─────────┤ ├──────────────────────────────────────────┤ (MDM Waves 2–5)
│
POD 3: ├───────────────────────────────────────────────────────────┤ (CDGC continuous)
| Milestone | Week | Gating Items |
|---|---|---|
| Contract Signature | 0 | Project kickoff authorization |
| Infrastructure Operational | 10 | All agents, VPN/firewall, DW schema, service accounts |
| Wave 1 Go-Live | 23 | 15–20 mappings, 1K rules, 200 catalog entries, UAT sign-off |
| Wave 2 Go-Live | 33 | 20 additional mappings, 2K rules, 5M MDM sample validated |
| Wave 3 Go-Live | 41 | 15 final mappings, 2K final rules, 35M golden records, full lineage |
| Wave 4 Go-Live (MDM) | 45 | MDM UAT complete, steward training, production cutover |
| Project Complete | 48 | Regression tests passed, hypercare started, project closure |
| Go-Live # | Week | Module(s) | Business Impact |
|---|---|---|---|
| #1: Wave 1 | 23 | CDI (IBM, Files), CDQ (1K rules), CDGC (200 tables) | Manual ETL fully automated; data quality visible |
| #2: Wave 2 | 33 | CDI (Databases), CDQ (expanded), CDGC (350 tables) | 70% data coverage; MDM foundation validated |
| #3: Wave 3 | 41 | CDI (Cloud), CDQ (complete 5K), CDGC (500 tables, lineage) | 100% data integration; full governance |
| #4: Wave 4 | 45 | MDM | Golden records operational; stewardship live |
If not met by end of Week 10, Wave 1 will slip proportionally.
| Dependency | Owner | Delivery By | Impact of Delay |
|---|---|---|---|
| VM Provisioning | CNHI IT Infrastructure | Week 5 | Agent installation delayed; critical path |
| OS Image & Patching | CNHI IT Infrastructure | Week 6 | Agent installation delayed |
| Firewall Rules | CNHI Security/Network | Week 7 | Agent connectivity delayed |
| Service Accounts (SQL Server, SharePoint, file shares) | CNHI IT Identity | Week 6 | Mapping testing delayed; Wave 1 slip |
| VPN Tunnel Setup (if chosen) | CNHI Network + Informatica | Week 8 | Connectivity validation delayed; performance tuning affected |
| SQL Server DW Provisioning | CNHI IT Infrastructure | Week 7 | DW design review and testing delayed |
| Source System Access (IBM, databases, file shares) | CNHI Data Stewards/IT | Week 6 | Data discovery and profiling delayed |
| Data Quality Rule Inventory | CNHI SMEs | Week 4 | Prioritization and planning delayed; estimated 5K rules |
| DW Design Sign-Off | CNHI Architecture | Week 5 | Build phase cannot start cleanly |
| Source Priority Confirmation | CNHI Executive Sponsor | Week 10 | Sprint planning for Wave 1 delayed |
| Dependency | Owner | Wave(s) | Impact of Delay |
|---|---|---|---|
| Source System Credentials (SQL Server logins, JDBC passwords, API tokens) | CNHI IT/Application Owners | All waves | Mapping tests blocked |
| Data Quality Rule Specifications (exact validation logic, priority, business context) | CNHI SMEs/Data Stewards | Wave 1 (Week 11), Wave 2 (Week 24), Wave 3 (Week 34) | DQ implementation delayed; reduced pass-rate targets |
| DW Schema Approval (star-schema design, table/column naming) | CNHI DBAs | Week 6–7 (before Wave 1 build) | Mapping design delayed; Wave 1 slip |
| Historical Data Availability (10 TB export from sources) | CNHI IT/Data Stewards | Wave 1 (Week 11) | Historical load testing delayed |
| Mini-UAT Participation (2 weeks per wave) | CNHI UAT Team | Weeks 21–22 (Wave 1), Weeks 32–33 (Wave 2), Weeks 40–41 (Wave 3) | Sign-off delayed; go-live date at risk |
| Dependency | Owner | Wave(s) | Impact of Delay |
|---|---|---|---|
| MDM Requirements Workshop (match criteria, survivorship rules, stewardship workflows) | CNHI Data Stewards + SMEs | Wave 0–1 (Weeks 1–23) | MDM design delayed; Wave 2 slip |
| Sample Data Set (5M beneficiary records, representative providers) | CNHI IT/Data Stewards | Wave 2 (Week 24) | MDM tuning delayed; thresholds not validated |
| Steward Team Availability (review/approve match results, resolve conflicts) | CNHI Data Stewards | Wave 2–3 (Weeks 24–41), Wave 4 (Weeks 42–45) | Golden record tuning blocked; go-live delayed |
| MDM Stewardship Training | Sutherland | Wave 4 (Weeks 42–45) | Workflow adoption delayed |
| Dependency | Owner | Wave(s) | Impact of Delay |
|---|---|---|---|
| Business Glossary (domain terms, definitions, mappings to physical assets) | CNHI Data Stewards/Domain Leads | Wave 1 (Week 11) | Catalog search/discovery limited; governance not actionable |
| Metadata Permissions & Access Model (who sees what in catalog) | CNHI IT Security | Wave 0 (Week 8) | Catalog cannot be deployed; access controls missing |
| Lineage Acceptance Criteria (what constitutes "complete" end-to-end lineage) | CNHI Governance Lead | Wave 0 (Week 5) | Lineage validation subjective; sign-off delays |
| Data Classification Rules (PII, confidential, retention) | CNHI Security/Compliance | Wave 1 (Week 12) | Masking policies incomplete; non-prod testing restricted |
| Dependency | Owner | Due | Impact of Delay |
|---|---|---|---|
| UAT Environment Sign-Off (all Waves 1–4 passed testing) | CNHI UAT Lead | Week 45 | Regression testing cannot start |
| Operator Training Completion | CNHI IT Operations | Week 47 | Hypercare will lack trained responders |
| Change Management Approvals (CNHI change advisory board) | CNHI Change Manager | Weeks 46–48 | Production cutover delayed; hypercare window shortened |
| Role / Team | Effort | Timing | Deliverables / Responsibilities |
|---|---|---|---|
| Executive Sponsor | 2–3 hrs/week | Weeks 0–48 | Decision-making authority; escalation; prioritization |
| IT Director | 3–5 hrs/week | Weeks 0–10 (Wave 0 peak); ongoing | Infrastructure procurement; security approvals; firewall rules |
| Business SMEs | 5–10 hrs/week | Waves 0–3 (peak Waves 1–2) | DQ rule definitions; business logic validation; UAT |
| Data Stewards | 5–10 hrs/week (Waves 0–2), 15–20 hrs/week (Waves 3–5) | Waves 0–5 | DQ remediation; MDM validation; golden record approval |
| DBAs | 3–5 hrs/week | Waves 0, 5 (peak); ongoing | DW design; performance tuning; index strategy |
| Network/Security | 5–10 hrs/week | Wave 0 (peak); ongoing | VPN tunnel; firewall rules; credential vaulting |
| UAT Teams | 10–20 hrs/week per wave | Waves 1–4 (2 weeks per wave) | Test case execution; sign-off; defect triage |
| Metric | Target | Wave Achievement | Measurement | Notes |
|---|---|---|---|---|
| Batch Window | ≤3 hours | Validated by Wave 5 | Job execution duration from start to DW load completion | Subject to source availability and network latency |
| DQ Pass Rate | 90% → 95% | Wave 1: ≥90%, Wave 2: ≥92%, Wave 3: ≥95% | % of records passing all applicable rules per wave | Targets are design objectives; actual rates depend on upstream remediation |
| MDM Match Coverage | ≥98% | Wave 2: 5M sample validated; Wave 3: 35M+ full load | % of input records successfully matched or identified as new | "Match coverage" = operational metric; precision/recall tuned during Waves 2–3 |
| Agent Availability | 99.5% | Operational SLA (active-active HA) | Uptime during nightly batch windows | Excludes CNHI-side network/source outages |
| Lineage Completeness | 100% source → DW | Wave 3 | End-to-end lineage for all 50+ mappings | Verified via manual audit + lineage reports |
| Outcome | Wave Enabled | Success Definition |
|---|---|---|
| Manual ETL Elimination | Wave 1 | IBM and file-based extracts fully automated; zero manual intervention required nightly |
| Data Quality Visibility | Wave 1 | Stewards can see DQ violations in real-time; remediation workflows active |
| Master Data Readiness | Wave 4 | Golden records in use by downstream systems; single-view-of-customer operational |
| Governance & Compliance | Wave 3 | Catalog searchable; lineage auditable; PDPL compliance demonstrable |
| Operational Self-Sufficiency | Wave 5 | CNHI operations team can run, monitor, and troubleshoot platform independently |
- ✅ All 8 Secure Agents operational and connected to IDMC
- ✅ VPN tunnel (if chosen) stable with latency < 50 ms
- ✅ SQL Server DW database created with approved schema
- ✅ All 4 IDMC module blueprints signed off
- ✅ Source priorities finalized
- ✅ DQ rule count confirmed (5K estimate vs. actual)
- ✅ All PODs ready to sprint
- ✅ 15–20 ETL mappings operational and scheduled
- ✅ 4–5 TB historical data loaded (100% reconciliation)
- ✅ 1,000 DQ rules live (≥90% pass rate)
- ✅ 200 tables cataloged
- ✅ PRODUCTION GO-LIVE: Week 23
- ✅ UAT sign-off received
- ✅ 35 total mappings operational
- ✅ 6–8 TB total data loaded
- ✅ 3,000 total DQ rules (≥92% pass rate)
- ✅ 350 tables cataloged
- ✅ 5M MDM sample successful
- ✅ PRODUCTION GO-LIVE: Week 33
- ✅ All 50+ mappings operational
- ✅ 10 TB total data loaded
- ✅ 5,000 total DQ rules (≥95% pass rate)
- ✅ 500 tables cataloged
- ✅ 35M+ golden records created
- ✅ Complete end-to-end lineage
- ✅ PRODUCTION GO-LIVE: Week 41
- ✅ 35M+ beneficiary golden records operational
- ✅ 25K+ provider golden records operational
- ✅ MDM Hub live with stewardship workflows
- ✅ Stewards trained and confident
- ✅ PRODUCTION GO-LIVE: Week 45
- ✅ End-to-end regression testing complete
- ✅ Performance validated (batch ≤3 hours)
- ✅ CNHI operations team certified
- ✅ Hypercare (3 weeks) initiated
- ✅ PROJECT COMPLETE: Week 48
| Phase | Process | Timeline |
|---|---|---|
| Plan & Design | Design documents reviewed and approved by CNHI architecture team | 1 week per document |
| Build & Test | Bi-weekly demos; feedback incorporated into next sprint | Per sprint (2 weeks) |
| UAT | Mini-UAT (2 weeks per wave) with CNHI business users | Per wave |
| Sign-Off | Formal written acceptance signed by CNHI sponsor or designee | Before go-live |
| Hypercare | 3-week post-go-live support; issue triage and resolution | Weeks 46–48 |
| Assumption | Rationale | Mitigation |
|---|---|---|
| Informatica Windows Server 2022 Support Confirmed | CNHI prefers Windows for ops alignment; Informatica may recommend Linux | Wave 0 dependency: written confirmation from Informatica before agent provisioning |
| Source System Access Available | Integration requires credentials and connectivity to IBM, SQL Server, SharePoint, APIs, etc. | Wave 0 discovery maps all access constraints; Wave 1 onboarding sequence sources with confirmed access |
| CNHI SME Availability | 5–20 hrs/week ongoing participation required | Executive sponsor ensures team commitment; steering committee escalates conflicts |
| Data Quality Rules Estimate (5,000) | Indicative; actual scope confirmed post-discovery | Wave 0 finalizes rule count; success measured by domain coverage, not rigid count |
| VPN Tunnel Available | IPSec option assumes CNHI network can provision tunnel by Week 8 | Fallback: internet egress via port 443 if VPN delayed; performance may vary |
| SQL Server DW Performance | DW tuning (indexes, partitions) assumes CNHI allows Sutherland recommendations | Wave 5 performance tuning; CNHI DBA executes recommendations |
| Secure Agent Capacity | Initial 2-agent sizing sufficient for Wave 1–2; scaling available for Wave 3+ | Wave 0 capacity planning; elastic scaling model in Wave 5 |
| Risk | Probability | Impact | Mitigation |
|---|---|---|---|
| VM Provisioning Delay | Medium | High (critical path) | Weekly dependency tracking; alternate resources available if needed |
| Source System Credential Challenges | Medium | High (blocks mapping tests) | Wave 0 discovery identifies access constraints; phased onboarding prioritizes available sources |
| DQ Rule Scope Explosion (actual > 5K) | Medium | Medium (Wave 1 slip) | Wave 0 rule prioritization limits Wave 1 to ~1K; later waves handle excess |
| MDM Sample Load Performance (slower than expected) | Low | Medium (Wave 2 slip) | Week 24 proof-of-concept; tuning adjustments before full load |
| Network Latency Issues | Low | Medium (SLA impact) | VPN tunnel provides deterministic path; internet fallback available |
| Steward Availability for MDM (overcommitted) | Medium | High (golden record delay) | Executive sponsor ensures team commitment; cross-training backup stewards |
| Informatica Module Feature Loss on Windows | Low | High (platform switch cost) | Wave 0 written confirmation; contingency Linux deployment plan |
- Duration: 48 weeks from contract signature through project closure
- Sutherland Team: 12–13 FTE specialists (variable per wave; peak Waves 1–3)
- Engagement Model: Fixed-scope, wave-based delivery with time-box per milestone
- Change Control: Scope changes managed via change request process; documented impact on timeline/budget
- Wave 1–4 Warranty: 30 days post-go-live defect rectification at no additional cost
- Hypercare: 3 weeks post-Wave-5 go-live (Week 46–48) on-call support (2 hrs/day response time)
- Post-Hypercare SLA: Optional AMS engagement available (separate statement of work)
- IDMC Licenses & IPUs: CNHI responsibility; Sutherland validates sizing against approved scope
- IPU Adjustment: If scope changes materially (additional sources, rules, data volume), IPU impact will be assessed; cost borne by CNHI
- License Key Management: CNHI provides; Sutherland configures
| Training Track | Audience | Duration | Timing |
|---|---|---|---|
| Infrastructure & Operations | IT Operations, DBAs | 3 days | Wave 5 (Weeks 46–47) |
| Data Integration & Pipelines | Developers, data engineers | 3 days | Wave 1 (post-go-live) + Wave 5 refresher |
| Data Quality | Stewards, SMEs | 2 days | Wave 1 (post-go-live) + Wave 5 |
| Master Data Management | Stewards | 2 days | Wave 4 (pre-go-live) + Wave 5 |
| Governance & Catalog | Business users, stewards | 1 day | Wave 3 (post-go-live) |
| Deliverable | Ownership Post-Project |
|---|---|
| IDMC Mappings & Configurations | CNHI (Sutherland provides runbooks for maintenance) |
| Data Warehouse Schema & Indexes | CNHI DBAs (Sutherland provides tuning recommendations) |
| Runbooks & Documentation | CNHI IT Operations |
| Source Code (if custom) | CNHI (Sutherland retains IP for reusable components) |
| Lineage & Governance Policies | CNHI (Sutherland defines initial structure) |
- Payment by Wave: Invoices upon milestone completion (Wave 0 Foundation → Wave 5 Closure)
- Pricing: [To be detailed in commercial proposal section]
- Optional Post-Project AMS: Separate SOW; includes monitoring, rule updates, new source onboarding, performance tuning
CNHI's enterprise data strategy extends beyond traditional BI into AI-powered decision-making and generative AI applications. Informatica IDMC, combined with Sutherland's implementation approach, creates the governance and data quality foundation that GenAI models depend on.
| AI Challenge | IDMC Solution | Benefit to CNHI |
|---|---|---|
| Data Lineage & Auditability | Complete end-to-end lineage (source → transformation → model input) | Explainability: trace any model prediction back to its data sources |
| Data Quality for Model Training | 5,000+ DQ rules, pass-rate scorecards | Cleaner training data = more accurate models |
| PII & Sensitive Data Protection | Classification tags, masking policies, audit trails | Compliant with PDPL; reduces model hallucination risk from PII leakage |
| Master Data Consistency | Golden records (35M+ beneficiaries, 25K+ providers) | Stable, deduplicated input to ML models (no bias from duplicate records) |
| Metadata & Feature Discovery | Comprehensive catalog (500+ assets) with glossary mapping | Data scientists can rapidly identify features; reduce model development time |
Example 1: Customer Analytics & Churn Prediction
- Input: Golden beneficiary records (MDM) + transaction data (CDI) + quality-validated flags (CDQ)
- Model: Train on cleansed, deduplicated data → predict churn risk
- Transparency: IDMC lineage documents exactly which sources/transformations fed the model
Example 2: Provider Network Optimization
- Input: Golden provider records (MDM) + service utilization (CDI) + performance metrics (CDQ)
- Model: Identify underperforming or redundant providers
- Governance: Classification tags ensure only authorized teams access sensitive provider data
Example 3: LLM Knowledge Repository Hygiene
- Input: Structured data (beneficiary policies, regulations) + unstructured (documents) → vector store
- Pipeline: IDMC ensures source data is clean, lineage-tracked, masked where needed
- Governance: Audit trail of what data went into knowledge base (critical for RegTech compliance)
| Area | Who Owns | How IDMC Helps |
|---|---|---|
| Data Preparation for ML | CNHI Data Science + Sutherland (optional AMS) | IDMC lineage & DQ provide clean inputs; reduce prep time |
| LLM Prompt Engineering | CNHI Data Science | Catalog + lineage visibility help identify features for few-shot examples |
| Model Monitoring & Drift | CNHI Operations + Data Science | IDMC metadata & DQ continue tracking source data quality post-model |
| Compliance & Audit | CNHI Compliance + Governance | IDMC lineage & classification tags simplify PDPL/audit responses |
Informatica & Enterprise Data Integration:
- 15+ years of data platform implementations across EMEA, Asia-Pacific, and Americas
- 50+ greenfield data warehouse and ETL modernization projects
- Certified Informatica implementation partners (CDI, CDQ, MDM, CDGC modules)
- Expertise in regulated industries: healthcare, financial services, government, telecommunications
Data Governance & Compliance:
- Experience implementing PDPL, GDPR, CCPA-aligned governance frameworks
- Catalog and lineage implementations supporting audit and compliance
- Master data management for identity resolution in regulated contexts
Regional Presence:
- Established operations in Middle East and North Africa (MENA)
- Local security clearance and compliance certifications
- Hybrid (onshore/offshore) delivery model with MENA-based support teams
- Solution Architect: Informatica Certified Professional (CDI/CDQ/MDM), AWS or Azure Cloud Architect
- POD Leads: Informatica Certified Developers (module-specific)
- All Team Members: Relevant cloud and security certifications (e.g., AWS Security, ISO 27001)
[Case Study 1: Healthcare Provider Integration]
- Client: Large Middle Eastern healthcare network (~500 hospitals)
- Challenge: 20+ source systems; fragmented patient records; compliance with local data residency laws
- Solution: IDMC + Sutherland; greenfield master patient index (30M+ records); 100% on-premises execution
- Result: 15% reduction in duplicate encounters; improved care coordination; PDPL-ready governance
[Case Study 2: Financial Services Master Data]
- Client: Regional bank (KSA-based; confidential NDA)
- Challenge: Multiple acquired banks; duplicate customer records; legacy core systems
- Solution: IDMC MDM; survivorship rules; stewardship workflows
- Result: Single customer view; 40% faster new product deployment; 25% reduction in risk management effort
| Dimension | Sutherland's Approach |
|---|---|
| Delivery Speed & Early Value | Parallel POD model delivers first production value Week 23 (not Week 52+); four incremental go-lives reduce risk |
| Data Sovereignty & PDPL Compliance | 100% on-premises execution; zero raw data moves to cloud; IDMC is orchestration only; transparent architecture |
| Operational Readiness | Hypercare + runbooks + training focus on CNHI self-sufficiency; not a "hand-off and abandon" approach |
| AI/LLM Future-Readiness | Governance, lineage, and data quality framework positions CNHI for safe, compliant GenAI pipelines |
| Hybrid Delivery Model | Combination of onshore expertise (Riyadh/KSA presence) and offshore scaling (India-based centers) maximizes efficiency and cost |
| Fixed-Wave Commitment | 48-week roadmap with gated, achievable milestones; reduced scope creep via sprint discipline |
Structure: Fixed-price, milestone-based payment per wave
| Phase | Duration | Deliverables | Proposed Cost |
|---|---|---|---|
| Wave 0 | Weeks 1–10 | Foundation, discovery, DW design, infrastructure | [TBD] |
| Wave 1 | Weeks 11–23 | CDI+CDQ, first production go-live | [TBD] |
| Wave 2 | Weeks 24–33 | Core databases, MDM sample, second go-live | [TBD] |
| Wave 3 | Weeks 34–41 | Cloud sources, complete CDGC, third go-live | [TBD] |
| Wave 4 | Weeks 42–45 | MDM production deployment | [TBD] |
| Wave 5 + Hypercare | Weeks 46–48 | Regression, optimization, 3-week hypercare | [TBD] |
| TOTAL (48 weeks) | — | Full end-to-end implementation | [TBD] |
Optional Post-Project:
- Managed Services (AMS): 12-month support, monitoring, rule updates, new source onboarding — [TBD] per month
- Secure Wave 0 completion on time — any delay cascades
- Maintain parallel POD momentum — weekly syncs essential; dependencies tracked daily
- Demonstrate tangible Wave 1 value — Week 23 go-live builds credibility for Waves 2–5
- Steward engagement during Waves 2–4 — golden record success depends on steward availability
- Executive sponsor empowered to remove roadblocks — VMs, firewall, credentials, approvals
- SME and steward time commitment — cannot be ad-hoc; must be prioritized
- Data governance model clarification in Wave 0 — enables faster governance implementation
- Source system access confirmed early — prevents mid-wave surprises
This proposal outlines a pragmatic, risk-managed path to transforming CNHI's data capabilities. By combining Informatica IDMC's cloud-based orchestration with on-premises Secure Agents and parallel POD delivery, Sutherland will:
✅ Deliver first production value in Week 23 (not 52+ weeks)
✅ Ensure 100% data residency in Saudi Arabia (PDPL-compliant)
✅ Automate manual ETL, establish data quality, and enable master data management
✅ Catalog and govern 500+ data assets with complete lineage
✅ Build a foundation for safe, trustworthy AI/LLM pipelines
✅ Hand over operational control to CNHI by Week 48 with confidence
The roadmap is ambitious yet achievable, grounded in Sutherland's 15+ years of enterprise data platform expertise and commitment to CNHI's success.
Document Version: 1.0
Date: January 2, 2026
Prepared by: Sutherland Presales Analytics Solution Team
For: CNHI Executive Leadership & RFP Evaluation Committee