SUTHERLAND PROPOSAL TO CNHI

Informatica IDMC Implementation for Enterprise Data Management

January 2026


EXECUTIVE SUMMARY

1.1 Business Transformation at a Glance

CNHI is modernizing its enterprise data capabilities by adopting Informatica Intelligent Data Management Cloud (IDMC) as the unified control plane for data integration, quality governance, and master data management. This greenfield implementation will:

  • Eliminate manual ETL workloads for IBM mainframe and file-based systems (Week 23 production value)
  • Establish data quality as a first-class operation with 5,000+ automated business rules across three prioritized waves
  • Create authoritative master data for 35M+ beneficiaries and 25K+ provider records, enabling single-customer-view and compliance
  • Catalog and govern 500+ data assets with end-to-end lineage and business glossary alignment
  • Ensure 100% data residency in the Kingdom of Saudi Arabia via on-premises Secure Agents, with IDMC serving purely as a cloud-based SaaS control plane

This approach combines cloud agility with on-premises data sovereignty, delivering a secure, compliant, operationally transparent platform that CNHI teams will own and extend confidently.

1.2 Why This Matters to CNHI

Challenge Today With IDMC
ETL Operations Manual, error-prone, resource-intensive Automated, resilient, governed
Data Quality Ad-hoc validation, low visibility 5,000+ rules, scorecards, real-time remediation
Master Data Fragmented beneficiary/provider records 35M+ golden records, single source of truth
Governance & Compliance Scattered documentation, audit friction Complete catalog, lineage, PDPL-ready
Future-Ready Data Ops Limited agility, siloed systems Extensible platform ready for AI/LLM pipelines

1.3 Key Innovation: Parallel POD Delivery Model

Traditional Sequential Approach → Bottlenecks, months of waiting, delayed value
Sutherland's Parallel POD Approach → Three specialized teams working simultaneously

  • POD 1 (CDI+CDQ): Data Integration & Quality — Weeks 1–48
  • POD 2 (MDM): Master Data Management — Weeks 24–48 (parallel with POD 1)
  • POD 3 (CDGC): Governance & Catalog — Weeks 11–48 (continuous)

Result: First production value in Week 23 (not Week 52+), and all four IDMC modules operational by Week 48.

1.4 Project at a Glance

Dimension Details
IDMC Modules Cloud Data Integration (CDI), Cloud Data Quality (CDQ), Master Data Management (MDM), Data Governance & Catalog (CDGC) — All 4 in scope
Delivery Model Wave-based incremental releases with 3 parallel PODs
Architecture Hybrid: IDMC cloud orchestration + on-premises Secure Agents (100% data residency)
Source Systems 8+ systems: IBM (CP4I), SQL Server, PostgreSQL, Oracle, SharePoint, APIs, file landing zones, and more
Data Volumes 10 TB historical + ongoing weekly/monthly batches
Environments Dev, Test, Prod (production with high availability)
Team Size 12–13 Sutherland specialists + CNHI SMEs/stewards
Total Duration 48 weeks (12 months) from contract to full handover
Production Go-Lives 4 incremental releases: Week 23 (CDI/CDQ), Week 33, Week 41, Week 45 (MDM)

1.5 Key Milestones & Production Value Timeline

Milestone Week What's Delivered Business Impact
Infrastructure Ready 10 Secure Agents operational, VPN/firewall, DW schema Foundation for rapid build
Wave 1 Go-Live 23 IBM + Files automation, 1,000 DQ rules, 200 catalog entries FIRST PRODUCTION VALUE: Manual ETL eliminated
Wave 2 Go-Live 33 Core databases (SQL Server, PostgreSQL, Oracle), 3,000 total DQ rules 70% data coverage operational
Wave 3 Go-Live 41 Cloud/external sources (SharePoint, APIs), 5,000 total DQ rules, complete lineage 100% CDI/CDQ/CDGC operational
MDM Go-Live 45 35M+ golden records, stewardship workflows Master data production-ready
Project Complete 48 Full hypercare, CNHI self-sufficient, all SLAs validated Ready for independent operations

2. SCOPE & DELIVERABLES

2.1 IDMC Modules In Scope

All four IDMC modules are included in this engagement, sequenced across waves to deliver early value while building toward comprehensive governance.

Cloud Data Integration (CDI) — POD 1 Lead

  • What: Ingest from 8+ source systems (IBM/CP4I, SQL Server, PostgreSQL, Oracle, SharePoint, APIs, files, etc.) into on-premises SQL Server DW
  • Design Objectives:
    • 50+ ETL/ELT mappings across three waves
    • 10 TB historical migration in Wave 0–1
    • Weekly/monthly batch processing with change-data-capture (CDC) foundation
    • Heterogeneous file support (CSV, JSON, Parquet, DB backups)
    • Error handling, quarantine patterns, reconciliation reports
  • Key Deliverables:
    • Dimensional data warehouse design (star schema)
    • 50+ production mappings with documentation
    • Batch scheduling framework
    • Historical load reconciliation reports
    • Incremental load patterns and restart logic
  • Wave Delivery: Waves 1, 2, 3 (15–20 mappings per wave, refined in operations)

Cloud Data Quality (CDQ) — POD 1 Lead

  • What: Translate CNHI's business rules into enforceable, observable data quality checks
  • Design Objectives:
    • Up to 5,000 business rules across three prioritized waves (P0 → P1 → P2)
    • Weekly profiling of 500+ tables
    • DQ scorecards with pass-rate dashboards
    • Violation tracking and remediation workflows
    • Steward-facing task queues
  • Approach: Rules are indicative targets subject to discovery. Wave 0 workshops will confirm actual rule count, prioritization, and implementation effort. Final rule volume may be adjusted per discovery outcome; success is measured by coverage of critical domains rather than rigid rule count.
  • Key Deliverables:
    • 5,000 rules (estimate) implemented across waves, with actual scope confirmed post-discovery
    • DQ scorecards (target ≥90% pass rate Wave 1, ≥95% Wave 3)
    • Violation dashboards and remediation trackers
    • Steward training and workflow documentation
  • Wave Delivery: Waves 1, 2, 3 (priority-based rule activation)

Master Data Management (MDM) — POD 2 Lead

  • What: Create and operate authoritative golden records for beneficiaries and providers
  • Design Objectives:
    • Match rules reflecting CNHI's data realities (noisy identifiers, multilingual names, variations)
    • Survivorship logic prioritizing authoritative sources per attribute
    • Stewardship workflows for complex matches requiring human judgment
    • Sample tuning (Wave 2, ~5M records) → full-scale loads (Wave 3)
    • Golden record creation with audit trails
  • Approach: Match coverage targets are qualitative (≥98% matching confidence on sample data) rather than rigid precision/recall commitments, allowing refinement during Waves 2–3. Success is measured by operational readiness and steward confidence in golden records.
  • Key Deliverables:
    • MDM match rules and survivorship hierarchies
    • 35M+ beneficiary golden records (wave 3–4 load)
    • 25K+ provider golden records
    • Stewardship workflows and approval processes
    • Sample load validation report (Wave 2)
    • Full-scale load reconciliation (Wave 3)
  • Wave Delivery: Waves 2, 3, 4 (sample → full-scale → production)

Cloud Data Governance & Catalog (CDGC) — POD 3 Lead

  • What: Inventory, catalog, classify, and trace all data assets and lineage
  • Design Objectives:
    • 500+ tables cataloged (estimate, subject to discovery)
    • Native scanners (SQL Server, SharePoint) + integration-derived metadata for unavailable scanners
    • End-to-end lineage from source → Secure Agent transformations → DW
    • Business glossary import and mapping to physical assets
    • Data classification (PII, confidential, retention rules)
    • Weekly metadata scans and updates
  • Approach: Catalog scope is discovery-driven. The goal is completeness of visibility rather than rigid table count; final scope will be confirmed during Wave 0 source profiling.
  • Key Deliverables:
    • 500+ tables in catalog (indicative, subject to discovery)
    • Lineage visualization end-to-end
    • Business glossary terms mapped to assets
    • Data classification tags
    • Governance workflows and stewardship assignments
    • Weekly metadata scan automation
  • Wave Delivery: Waves 1, 2, 3 (incremental catalog expansion)

2.2 Source Systems & Flexible Prioritization

Eight or more source systems will be integrated across three waves. Priorities can be adjusted during Wave 0 based on CNHI's evolving business needs.

# Source System Type Integration Method Default Priority Default Wave Flexibility
1 IBM (DB2, AS/400) Mainframe Via CP4I 🔴 Critical Wave 1 Fixed (manual ETL elimination)
2 File Landing Zones (CSV, JSON, Parquet) Files SFTP/shared folder connector 🔴 Critical Wave 1 Fixed (manual ETL elimination)
3 SQL Server Data Mart RDBMS JDBC 🟡 High Wave 1 Can move to Wave 2 if needed
4 PostgreSQL RDBMS JDBC 🟡 High Wave 2 Flexible—can swap with Oracle
5 Oracle Database RDBMS JDBC 🟡 High Wave 2 Flexible—can move to Wave 3
6 SharePoint Online Cloud SaaS OAuth 2.0 connector 🟠 Medium Wave 3 Flexible—can accelerate to Wave 2
7 REST/SOAP APIs External REST/SOAP connectors 🟠 Medium Wave 3 Flexible—can accelerate if business urgent
8 Oracle ERP ERP JDBC 🔵 Low/Deferred Future Can move into Wave 2/3 if access available
+ Additional emerging sources (MongoDB, email, etc.) Varied TBD per connector 🔵 Backlog Future Added as needed in operations phase

Flexibility Model: During Wave 0, CNHI can re-order Wave 2 and Wave 3 sources without jeopardizing delivery, provided core Wave 1 sources (IBM, Files) remain fixed. Sutherland will support this agility via sprint-based scope control and transparent dependency tracking.

2.3 Infrastructure & Network Deliverables

Component Specification Purpose CNHI vs. Sutherland
Secure Agent VMs (Prod) 2 VMs @ 16 vCPU, 64 GB RAM, 1 TB SSD each (CDI/CDQ group + MDM group) High-availability on-premises execution CNHI provisions; Sutherland installs/configures
Secure Agent VMs (Non-Prod) 2 VMs @ 8–16 vCPU, 32–64 GB RAM, 500 GB SSD (Dev + Test) Right-sized development/testing CNHI provisions; Sutherland installs/configures
Agent Groups DEV, TEST, PROD-CDI-CDQ (POD 1), PROD-MDM (POD 2) Workload isolation & environment separation Sutherland designs & configures
Network Connectivity IPSec site-to-site VPN (AES-256) + TLS 1.2+ HTTPS (port 443) — VPN preferred; internet egress fallback Secure outbound tunnel from data center → IDMC cloud CNHI network + Informatica; Sutherland validates
SQL Server Data Warehouse 15–20 TB capacity, TDE encryption On-premises target repository CNHI provisions & maintains; Sutherland designs schema & tunes performance
OS & Patching Windows Server 2022 (preferred) or RHEL Linux (where Informatica-confirmed compatible) Secure Agent host OS CNHI provides; Sutherland validates compatibility in Wave 0
Monitoring & Alerting IDMC native monitoring + local OS metrics (CPU, memory, network) Operational visibility Sutherland configures dashboards; CNHI operates

Key Assumptions:

  • Informatica will confirm in writing (Wave 0 dependency) that all required CDI/CDQ/MDM/CDGC connectors and modules are fully supported on Windows Server 2022 for the Saudi Arabia regional tenant.
  • VPN tunnel infrastructure (IPSec endpoints, key management) is CNHI's responsibility; Sutherland assists with validation and monitoring configuration.
  • SQL Server DW hardware, patching, and availability are CNHI-owned; Sutherland provides performance tuning support (indexing, partitioning, query optimization, maintenance job configuration).

2.4 Data Warehouse Performance & SLA Framework

Metric Design Objective Wave Achievement Notes
Nightly Batch Window ≤3 hours for full daily processing (CDC + quality checks) Target by Wave 1 go-live Subject to source availability and network latency; will be jointly tuned during Week 23 cutover and Wave 2 expansion
DQ Rule Pass Rate Wave 1: ≥90% Wave 1: ≥90%; Wave 2: ≥92%; Wave 3: ≥95% Targets are design objectives, not contractual commitments; actual rates depend on upstream data remediation (CNHI responsibility)
MDM Match Coverage ≥98% of records matched with ≥90% confidence Validated in Wave 2 sample (5M records), refined by Wave 3 full load "Match coverage" = % of input records successfully matched to a golden record or correctly identified as new; precision/recall tuned during Wave 2
Catalog Completeness 500+ assets cataloged with lineage Phased: 200 in Wave 1, 350 by Wave 2, 500+ by Wave 3 Subject to actual source inventory discovered in Wave 0
Agent Availability 99.5% uptime (high-availability configuration, 2 agents per prod group) Measured across nightly batch windows Excludes CNHI-side network outages or source system unavailability

SLA Philosophy: These metrics are design targets and operational objectives that Sutherland and CNHI will jointly tune during the project. Success is measured by continuous improvement and operational readiness, not rigid contractual pass-fail thresholds. Any variance (e.g., 92% vs. 95% DQ pass rate, or batch window 3.5 vs. 3 hours) will be addressed through optimization sprints and root-cause analysis, not penalties.

2.5 Explicitly Out of Scope

Activity Why Out of Scope CNHI Ownership
Source System Modifications Applications own their data contracts; Sutherland integrates as-is CNHI decides if upstream systems need changes to support IDMC pipelines
Data Remediation at Source DQ identifies issues; fixing them upstream is a business/app decision CNHI owns root-cause analysis and remediation in source systems
Enterprise Governance Policies Organization-level data governance, data ownership, stewardship models CNHI defines; Sutherland enforces within IDMC configuration
BI Tool Development Power BI, Tableau, or other reporting layer CNHI builds reports on DW; Sutherland delivers DW with optimized schemas
SQL Server DW Provisioning & Patching Infrastructure is CNHI's responsibility CNHI provisions, patches, backs up; Sutherland tunes performance and design
Change Management / User Adoption Organizational change is external to technical delivery CNHI runs adoption programs; Sutherland provides training
LLM / GenAI Model Training AI engineering is adjacent to data pipelines Sutherland ensures data lineage and quality for AI inputs; CNHI builds models
Post-Wave-5 Managed Services (AMS) Base engagement covers delivery + hypercare only Optional post-project AMS is separate engagement (see Section 10: Engagement Terms)

3. SOLUTION ARCHITECTURE

3.1 Design Philosophy: Cloud Control Plane + On-Premises Execution

Core Principle: IDMC is a SaaS orchestration and governance layer (cloud-based). All data processing, transformation, and quality checks run on on-premises Secure Agents. Data never leaves CNHI's network boundary unless explicitly authorized and masked.

┌─────────────────────────────────────────────────────────────────┐
│                     INFORMATICA IDMC (Cloud)                     │
│  • Design Studio (pipeline authoring)                            │
│  • Job Scheduler & Orchestration                                │
│  • Monitoring, Logs, Lineage                                    │
│  • Governance, Catalog, Glossary                                │
│  • (Saudi-hosted GCP instance for PDPL compliance)              │
└──────────────────────────┬──────────────────────────────────────┘
                           │ (Outbound-initiated TLS 1.2+ HTTPS)
                           │ (No inbound ports; metadata only)
                           │
┌──────────────────────────┴──────────────────────────────────────┐
│            CNHI DATA CENTER (On-Premises)                       │
├─────────────────────────────────────────────────────────────────┤
│                                                                 │
│  ┌────────────────────────────────────────────────────────┐    │
│  │  Secure Agent Groups (VMs, Windows Server 2022)        │    │
│  ├────────────────────────────────────────────────────────┤    │
│  │ POD 1: CDI/CDQ Group (2 agents HA)                     │    │
│  │   ├─ Read from IBM, Files, SQL Server, etc.           │    │
│  │   ├─ Apply transformations, DQ rules                  │    │
│  │   ├─ Load SQL Server DW                               │    │
│  │   └─ Orchestrated by IDMC cloud                       │    │
│  │                                                        │    │
│  │ POD 2: MDM Group (2 agents HA)                        │    │
│  │   ├─ Read from DW (integrated data)                   │    │
│  │   ├─ Execute match/merge logic                        │    │
│  │   ├─ Create/update golden records                     │    │
│  │   └─ Orchestrated by IDMC cloud                       │    │
│  └────────────────────────────────────────────────────────┘    │
│                                                                 │
│  ┌────────────────────────────────────────────────────────┐    │
│  │  Source Systems (Unchanged)                            │    │
│  ├────────────────────────────────────────────────────────┤    │
│  │ • IBM DB2, AS/400 (via CP4I)                           │    │
│  │ • SQL Server, PostgreSQL, Oracle (JDBC)               │    │
│  │ • SharePoint, APIs (OAuth, REST)                      │    │
│  │ • File Landing Zones (SFTP, SMB)                      │    │
│  │ • Email, MongoDB, custom connectors (as needed)       │    │
│  └────────────────────────────────────────────────────────┘    │
│                                                                 │
│  ┌────────────────────────────────────────────────────────┐    │
│  │  SQL Server Data Warehouse (Target)                    │    │
│  ├────────────────────────────────────────────────────────┤    │
│  │ • Dimensional schema (star: facts + dimensions)        │    │
│  │ • 15–20 TB capacity, TDE encryption                   │    │
│  │ • Optimized for analytics (indexes, partitioning)     │    │
│  │ • Performance-tuned by Sutherland                     │    │
│  └────────────────────────────────────────────────────────┘    │
│                                                                 │
└─────────────────────────────────────────────────────────────────┘

3.2 Connectivity & Security Posture

Network Connectivity Options

Option 1: IPSec Site-to-Site VPN (Recommended)

  • How: Dedicated encrypted tunnel from CNHI data center to Informatica's Saudi GCP instance
  • Protocol: IPSec with AES-256 encryption, IKEv2
  • Benefits:
    • Deterministic latency and throughput
    • No public IP exposure
    • Double encryption (VPN + TLS)
    • Easier traffic inspection and monitoring
    • Supports future multi-tenancy scenarios
  • Effort: CNHI network team + Informatica provision endpoints; Sutherland validates configuration and performance

Option 2: Outbound HTTPS (Internet Egress)

  • How: Secure Agents initiate TLS 1.2+ HTTPS connections on port 443 to Informatica cloud endpoints
  • Benefits:
    • Simple, immediate deployment (no VPN provisioning)
    • Works with standard corporate firewalls
    • Lower infrastructure overhead
  • Trade-off: Latency variability, requires public IP whitelisting
  • Fallback: Recommended only if VPN unavailable

CNHI's Choice in Wave 0: Sutherland will validate both options and recommend VPN as the primary path based on security best practices and latency requirements. Final selection will be jointly made during infrastructure workshops.

Data Movement & Masking

Scenario What Flows Encryption Masking
Normal Operation Commands, job status, logs, metadata, counters IPSec + TLS 1.2+ Not needed (metadata only)
Administrative Preview Sample records for troubleshooting (rare) IPSec + TLS 1.2+ PII masked by policy
Non-Production Testing Full copies of non-sensitive data (Dev/Test) IPSec + TLS 1.2+ All PII masked
Compliance Audit Lineage reports, lineage graphs (PDPL/audit) IPSec + TLS 1.2+ Aggregated; no individual records

Golden Rule: Raw beneficiary or provider data never traverses CNHI's network boundary in unencrypted or unmasked form.

3.3 High-Availability & Scalability

Production Agent Groups (POD 1 & POD 2)

Each production POD runs two Secure Agents in active-active configuration:

  • Agent 1: Primary execution, handles 50% of workload
  • Agent 2: Standby, assumes full workload if Agent 1 fails
  • Failover: Automatic; transparent to IDMC orchestration
  • Data Consistency: Shared state via IDMC cloud coordination

Capacity Management:

  • Wave 1: 2 agents per group sufficient for initial data loads and batch processing
  • Wave 2–3: If batch windows exceed SLA or job queues grow, add third agent (elastic scaling)
  • Operations: CNHI can add/remove agents per resource availability and workload

Non-Production Environments

  • Dev & Test: Single agent per environment initially; can scale if needed
  • Promotion Discipline: Same configuration across Dev → Test → Prod ensures reliability

3.4 OS & Platform Alignment

Secure Agent OS Preference:

  • Windows Server 2022 (preferred) — aligns with CNHI's Microsoft-centric operations
  • Red Hat Enterprise Linux 8.x (supported alternative) — where CNHI prefers Linux

Wave 0 Dependency: Informatica will provide written confirmation that all required connectors and modules (CDI, CDQ, MDM, CDGC) are fully supported on Windows Server 2022 for the Saudi Arabia region, with no feature loss vs. Linux. If variance exists, Sutherland and CNHI will decide on a case-by-case basis.


4. DELIVERY APPROACH: WAVES & PARALLEL PODs

4.1 Why Waves + Parallel PODs?

Waves deliver incremental business value and reduce risk. Parallel PODs prevent bottlenecks and accelerate time-to-value.

Aspect Traditional Sequential Sutherland Wave + POD Model
CDI Completion All sources ready, then start CDQ POD 1: Waves 1–3 concurrent with POD 2 MDM work
Time to First Value 52+ weeks (after all modules complete) Week 23 (Wave 1 go-live: manual ETL automated)
Risk Late discovery = cascade delays Early wins reduce scope uncertainty
Team Utilization Sequential = idle periods Parallel = continuous momentum
Change Agility Hard to re-prioritize sources Sprint-based, re-prioritize week-to-week

4.2 Wave Overview

Wave Weeks Focus PODs Active Production Go-Live Key Business Value
Wave 0 1–10 Foundation, discovery, DW design, infrastructure All (setup) Solid foundation, detailed requirements
Wave 1 11–23 IBM + Files automation, 1K DQ rules, catalog foundation POD 1, POD 3 Week 23 Manual ETL eliminated
Wave 2 24–33 Core databases, 2K DQ rules, MDM sample load POD 1, POD 2, POD 3 Week 33 70% data coverage; MDM tuning underway
Wave 3 34–41 Cloud/external sources, 2K final DQ rules, full MDM load POD 1, POD 2, POD 3 Week 41 100% CDI/CDQ/CDGC; golden records ready
Wave 4 42–45 MDM production deployment POD 2 Week 45 Master data operational
Wave 5 46–48 Regression testing, optimization, handover All Week 48 CNHI self-sufficient

4.3 WAVE 0: Foundation & Design (Weeks 1–10)

Objective: Build solid infrastructure, detailed discovery, data warehouse design, and technical blueprints across all four IDMC modules.

Key Activities

Category Activities Duration Deliverable
Discovery & Requirements Source system profiling (8+ sources), data quality rule inventory (estimate 5K), governance glossary assembly, dimensional modeling workshops Weeks 1–3 Discovery Summary Report, Source Inventory Spreadsheet, DQ Rule Priorities (P0/P1/P2)
DW Design Dimensional star-schema design, physical schema (tables, columns, keys), indexing strategy, partitioning approach Weeks 2–4 Data Warehouse Design Document, ERDs, Data Dictionary
Technical Blueprints CDI approach per POD 1, CDQ approach per POD 1, MDM match/survivorship per POD 2, CDGC catalog & lineage per POD 3 Weeks 3–5 Technical Architecture Document (4 modules), proof-of-concept demo (sample mapping)
Infrastructure Setup VM provisioning (8 VMs total: 4 Prod, 2 Test, 2 Dev), OS installation, Secure Agent installation, firewall whitelisting, optional VPN tunnel provisioning Weeks 1–8 Infrastructure As-Built Document, Network Topology Diagram, Agent Health Checklist
Governance & Access Service account creation (SQL Server, SharePoint, APIs, file shares), IDMC tenant access roles defined, network security review, monitoring setup Weeks 3–8 Service Account Inventory, Access Control Matrix, Monitoring Dashboard

Wave 0 Deliverables

Deliverable Description Acceptance By
Discovery Summary Report All 8+ sources documented: schemas, volumes, growth rates, known data issues, business rules, integration constraints CNHI IT Director
Data Warehouse Design Document Dimensional model (star schema), physical schema, data dictionary, ETL framework, index/partition strategy CNHI BAs + Steering Committee
DQ Rule Catalog 5,000 rules estimated, prioritized by wave (Wave 1: ~1K, Wave 2: ~2K, Wave 3: ~2K), with business context and validation logic CNHI SMEs
MDM Requirements Document Match criteria per domain, survivorship rules, stewardship workflows, sample match strategy CNHI Data Stewards
Technical Architecture Document Module-by-module design (CDI, CDQ, MDM, CDGC), agent group strategy, security posture, performance targets CNHI Architecture Review Board
Infrastructure As-Built VMs, agent groups, network topology, VPN config (if chosen), monitoring setup; agents ✅ operational and connected CNHI IT & Security
Source Priority Confirmation Final wave assignments per source (Wave 1 fixed: IBM + Files; Waves 2–3 flexible per CNHI business needs) CNHI Executive Sponsor

Wave 0 Exit Criteria

  • ✅ All 8 Secure Agents operational and heartbeat confirmed with IDMC
  • ✅ VPN tunnel stable (if chosen) with latency < 50 ms
  • ✅ SQL Server DW database created with base schema
  • ✅ All 4 IDMC module blueprints approved
  • ✅ Source priorities finalized (IBM + Files in Wave 1, others re-orderable in Waves 2–3)
  • ✅ DQ rule count finalized and prioritized (actual vs. 5K estimate confirmed)
  • ✅ All POD teams mobilized and ready to sprint

4.4 WAVE 1: Automate Manual ETL — IBM & Files (Weeks 11–23)

Objective: Deliver first production value by automating CNHI's most painful manual ETL workloads (IBM mainframe and file-based loads).

🚀 Production Go-Live: Week 23

Scope

Component What Business Value
IBM Sources IBM DB2/AS/400 via Cloud Pak for Integration; ~2–3 TB historical Eliminate mainframe manual extracts
File Sources CSV, JSON, Parquet, DB backups from SFTP/shared folders; ~1–2 TB historical Automate file processing
SQL Server Existing data mart; supporting source Integrated into DW
DQ Rules 1,000 P0 rules (highest priority: identity, mandatory fields, type/range checks) Data quality at source
Catalog 200 tables cataloged with basic lineage Data discovery enabled

Timeline (13 weeks)

Weeks POD 1 (CDI+CDQ) POD 2 (MDM) POD 3 (CDGC)
11–14 CP4I connectivity, 5 IBM mappings, 500 DQ rules, SQL testing MDM requirements workshops Catalog IBM, File sources
15–18 File automation, 10 file mappings, 500 DQ rules, SQL integration MDM requirements workshops Catalog SQL Server
19–20 Hardening, testing all pipelines, error handling Lineage validation
21–22 Mini-UAT (2 weeks): CNHI UAT team executes test cases UAT support
23 PRODUCTION GO-LIVE Catalog live, lineage operational

Bi-weekly Sprint Demos: Weeks 12, 14, 16, 18, 20 to CNHI stakeholders

Wave 1 Deliverables

Deliverable Acceptance Criteria
15–20 ETL Mappings IBM, Files, SQL Server → DW; tested; documented; scheduled
4–5 TB Historical Data Loaded Reconciliation report shows 100% match
1,000 DQ Rules Live Pass rate ≥90% on Wave 1 data; violations tracked in detail
200 Tables Cataloged Searchable in IDMC catalog; business users can discover assets
Production Go-Live Report First nightly batch successful; SLAs monitored
UAT Sign-Off CNHI business users formally accept Wave 1 solution

Wave 1 Exit Criteria

  • ✅ 15–20 mappings operational and scheduled nightly
  • ✅ 4–5 TB historical data loaded (100% reconciliation)
  • ✅ 1,000 DQ rules live (≥90% pass rate)
  • ✅ 200 tables cataloged with lineage
  • ✅ UAT sign-off received from CNHI
  • PRODUCTION GO-LIVE: Week 23First Business Value Delivered

4.5 WAVE 2: Core Databases (Weeks 24–33)

Objective: Add PostgreSQL and Oracle; expand DQ rules; begin MDM hands-on development.

🚀 Production Go-Live: Week 33 | Cumulative: 70% Data Coverage

Scope

Component What Business Value
CDI — Databases PostgreSQL, Oracle → DW; ~2–3 TB historical Expand data integration coverage
CDQ — Expanded Rules 2,000 P1 rules (business semantics: standardization, formatting, cross-field checks) Broader quality coverage
CDGC — Expanded Catalog 150 additional tables (350 total); extended lineage Enhanced data discovery
MDM — Sample Load 5M beneficiary records sample; match tuning; algorithm validation MDM foundation (parallel with POD 1)

Timeline (10 weeks)

Weeks POD 1 (CDI+CDQ) POD 2 (MDM) POD 3 (CDGC)
24–27 PostgreSQL, Oracle design; 10 mappings started 5M sample load initiated; match rules tuned Catalog additional sources
28–30 2,000 DQ rules implemented; testing Match threshold tuning; precision/recall validation Lineage expansion
31 Error handling hardening UAT preparation
32–33 Mini-UAT (2 weeks) UAT support
33 PRODUCTION GO-LIVE Sample load validated Catalog live

Wave 2 Deliverables

Deliverable Acceptance Criteria
20 Additional Mappings PostgreSQL, Oracle → DW (35 total mappings)
2–3 TB Additional Data Reconciliation 100%
2,000 Additional DQ Rules Pass rate ≥92% (3,000 total rules)
350 Total Tables Cataloged Business users utilizing catalog for discovery
5M MDM Sample Load Match algorithm validated; coverage ≥95%
UAT Sign-Off CNHI accepts Wave 2

Wave 2 Exit Criteria

  • ✅ 35 total mappings operational
  • ✅ 6–8 TB total data loaded
  • ✅ 3,000 total DQ rules (≥92% pass rate)
  • ✅ 350 tables cataloged
  • ✅ 5M MDM sample successful (match coverage ≥95%)
  • PRODUCTION GO-LIVE: Week 33

4.6 WAVE 3: Cloud & External Sources (Weeks 34–41)

Objective: Complete all CDI/CDQ/CDGC modules; execute full-scale MDM load.

🚀 Production Go-Live: Week 41 | Cumulative: 100% CDI/CDQ/CDGC

Scope

Component What Business Value
CDI — Cloud/External SharePoint, APIs, additional sources; ~2–3 TB Complete data integration
CDQ — Complete Rules 2,000 P2 rules (cross-record, referential, extended checks); 5,000 total Full quality coverage
CDGC — Complete Catalog 150 additional tables (500 total); full end-to-end lineage Complete governance
MDM — Full Load 35M beneficiary + 25K provider full load; golden record creation Complete MDM operational

Timeline (8 weeks)

Weeks POD 1 (CDI+CDQ) POD 2 (MDM) POD 3 (CDGC)
34–36 SharePoint OAuth; API connectors; 15 final mappings Full 35M load initiated Catalog completion
37–39 2,000 final DQ rules; extended checks Golden record tuning; stewardship workflow testing Lineage finalization
40 Hardening and testing Final validation
41 PRODUCTION GO-LIVE Full load completed, ready for UAT Catalog live

Wave 3 Deliverables

Deliverable Acceptance Criteria
15 Final Mappings All 50+ mappings operational
10 TB Total Historical Data Complete data loaded and reconciled
5,000 Total DQ Rules Pass rate ≥95% overall
500 Total Tables Cataloged Complete catalog
Complete Lineage End-to-end lineage visible for compliance/impact analysis
35M+ Golden Records (MDM) Ready for production UAT
UAT Sign-Off (CDI+CDQ+CDGC) CNHI accepts Wave 3

Wave 3 Exit Criteria

  • ✅ All 50+ mappings operational
  • ✅ All 10 TB data loaded
  • ✅ All 5,000 DQ rules live (≥95% pass rate)
  • ✅ All 500 tables cataloged
  • ✅ Complete lineage documented
  • ✅ 35M+ golden records created
  • PRODUCTION GO-LIVE: Week 41

4.7 WAVE 4: MDM Production Deployment (Weeks 42–45)

Objective: Cutover from sample to full operational MDM.

🚀 MDM Production Go-Live: Week 45

Timeline (4 weeks)

Week Activity Owner
42 Golden record validation with CNHI SMEs; workflow testing; steward training begins POD 2 + CNHI stewards
43–44 MDM UAT (2 weeks): Stewards test conflict resolution, workflow, approval processes POD 2 + CNHI stewards
45 MDM Production Go-Live: Golden records operational; stewardship live POD 2

Wave 4 Deliverables

Deliverable Acceptance Criteria
35M+ Beneficiary Golden Records ≥98% match coverage; production-ready
25K+ Provider Golden Records ≥98% match coverage; production-ready
MDM Hub Operational Stewardship workflows live
Stewards Trained Stewards can resolve conflicts independently
UAT Sign-Off (MDM) CNHI stewards accept MDM solution

Wave 4 Exit Criteria

  • ✅ 35M+ beneficiary records (≥98% coverage)
  • ✅ 25K+ provider records (≥98% coverage)
  • ✅ MDM Hub operational
  • ✅ Stewards trained
  • MDM PRODUCTION GO-LIVE: Week 45

4.8 WAVE 5: Final Integration & Handover (Weeks 46–48)

Objective: End-to-end testing, optimization, operational readiness, project closure.

✅ Complete Solution Operational: Week 48

Timeline (3 weeks)

Week Activity Owner
46 End-to-end regression tests; performance tuning; admin training All PODs
47 User training finalized; runbooks reviewed; final optimization All PODs
48 Hypercare kickoff; operations handover; project closure Sutherland + CNHI

Wave 5 Deliverables

Deliverable Acceptance Criteria
Regression Test Report All end-to-end tests passed
Performance Report Batch window ≤3 hours; SLAs met
Runbooks CNHI operations can run platform independently
Training Records Admin + user training completed; sign-offs received
Hypercare Log No critical open issues; lessons learned documented
Project Closure Report Steering committee formal approval

Wave 5 Exit Criteria

  • ✅ End-to-end regression complete
  • ✅ Performance validated (batch window ≤3 hours)
  • ✅ CNHI operations team certified
  • ✅ 3-week hypercare complete
  • PROJECT COMPLETE: Week 48

5. TEAM STRUCTURE & POD ORGANIZATION

5.1 Delivery Organization Overview

Sutherland commits a dedicated core team of 12–13 specialists, organized into three parallel PODs with shared leadership services.

┌─────────────────────────────────────────────────────────┐
│     SUTHERLAND DELIVERY LEADERSHIP (Shared)             │
├─────────────────────────────────────────────────────────┤
│ • Solution Architect (1) — overall design, non-functional requirements |
│ • Project Coordinator (1) — sprint planning, risk/dependency tracking |
│ • Infrastructure Engineer (1) — VMs, agents, connectivity, monitoring |
│ • Technical Writer (1) — runbooks, training, documentation |
└─────────────────────────────────────────────────────────┘
                            │
         ┌──────────────────┼──────────────────┐
         │                  │                  │
    ┌────▼─────┐       ┌────▼─────┐       ┌────▼─────┐
    │  POD 1   │       │  POD 2   │       │  POD 3   │
    │ CDI+CDQ  │       │   MDM    │       │  CDGC    │
    └──────────┘       └──────────┘       └──────────┘
    (8–9 people)       (4–5 people)       (2–3 people)

5.2 POD 1: Data Integration & Quality (CDI+CDQ) — 8–9 Resources

Charter: Design and build all ETL pipelines, data quality rules, and operational frameworks.

Role FTE Responsibilities
CDI/CDQ Technical Lead 1.0 Designs integration patterns; reviews code; mentors developers; owns performance tuning
Integration Developers 3.0 Build and maintain mappings; design error handling; implement CDC frameworks
Data Quality Specialists 2.0 Translate business rules into IDMC tasks; design scorecards; build remediation workflows
Catalog Specialist 1.0 (Shared with POD 3) Captures metadata from CDI pipelines; maintains lineage
QA Engineer 1.0 Functional test coverage; UAT coordination; error handling validation

Engagement Duration: Weeks 1–48 (full program)

Peak Workload: Waves 1–3 (active development); Wave 4 (support); Wave 5 (regression/optimization)

5.3 POD 2: Master Data Management (MDM) — 4–5 Resources

Charter: Design and implement match rules, survivorship logic, and stewardship workflows.

Role FTE Responsibilities
MDM Technical Lead 1.0 Designs match algorithms; configures survivorship rules; performance tunes; owns hub operations
MDM Specialists 2.0 Configure match algorithms; tune thresholds; design golden record structures; validate sample loads
QA Engineer 1.0 Validates match coverage; tests stewardship workflows; UAT coordination

Engagement Duration: Weeks 1–10 (planning), Weeks 24–48 (active development + go-live)

Peak Workload: Waves 2–4 (sample tuning → full load → production deployment)

5.4 POD 3: Governance & Catalog (CDGC) — 2–3 Resources

Charter: Manage cataloging, metadata harvesting, lineage, and governance workflows.

Role FTE Responsibilities
Catalog & Governance Lead 1.0 Designs catalog strategy; schedules scanners; owns lineage; maintains governance policies
Catalog/Metadata Specialist 1.0 (Shared with POD 1) Harvests metadata; maps glossary terms; validates lineage

Engagement Duration: Weeks 1–48 (continuous)

Peak Workload: Waves 1–3 (catalog expansion); Waves 4–5 (optimization)

5.5 Shared Leadership Roles

Role FTE Responsibilities
Solution Architect 1.0 Oversees non-functional requirements (security, availability, performance); reviews key designs; resolves architecture questions; escalation point
Project Coordinator 1.0 Sprint planning; status reporting; dependency tracking; risk management; steering committee coordination
Infrastructure Engineer 1.0 VM provisioning, OS hardening, agent installation, network troubleshooting, monitoring setup
Technical Writer 1.0 Runbooks, configuration guides, training materials, lessons learned documentation

5.6 Ways of Working

Cadence Activity Participants
Weekly Cross-POD sync (1 hour) All POD leads + shared leadership
Bi-Weekly Sprint demos (1.5 hours) All Sutherland + CNHI stakeholders
Bi-Weekly Steering committee (1 hour) Leadership + CNHI executive sponsor
Weekly Dependency tracking review Project coordinator + POD leads
Per-Demand Architecture reviews Solution architect + relevant POD

5.7 CNHI Team Expectations

CNHI Role Time Commitment Key Responsibilities
Executive Sponsor 2–3 hrs/week Prioritize decisions; remove roadblocks
IT Director 3–5 hrs/week Infrastructure provisioning; security approvals
Business SMEs 5–10 hrs/week Define DQ rules; validate mappings; prioritize sources
Data Stewards 5–10 hrs/week (Wave 0–2), 15–20 hrs/week (Wave 3–4) Own DQ remediation; validate MDM golden records; run stewardship workflows
DBAs 3–5 hrs/week DW design review; performance tuning; index maintenance
Network & Security 5–10 hrs/week (Wave 0) VPN provisioning; firewall rules; security validation
UAT Teams 10–20 hrs/week (per wave) Execute test cases; sign-off on deliverables

6. TIMELINE & MILESTONES

6.1 Wave Execution Timeline

Week    1         10        20        30        40        48
        │         │         │         │         │         │
Wave 0: ├─────────┤ (Foundation)
        │
Wave 1: │         ├─────────────────────┤ (IBM + Files → Prod Week 23)
        │
Wave 2: │         │                     ├──────────────────┤ (DBs → Prod Week 33)
        │
Wave 3: │         │                     │                  ├────────┤ (Cloud → Prod Week 41)
        │
Wave 4: │         │                     │                  │        ├──┤ (MDM → Prod Week 45)
        │
Wave 5: │         │                     │                  │        │  ├─┤ (Handover → Week 48)
        │
POD 1:  ├─────────────────────────────────────────────────────────────┤ (CDI+CDQ continuous)
        │
POD 2:  ├─────────┤      ├──────────────────────────────────────────┤ (MDM Waves 2–5)
        │
POD 3:  ├───────────────────────────────────────────────────────────┤ (CDGC continuous)

6.2 Major Milestones

Milestone Week Gating Items
Contract Signature 0 Project kickoff authorization
Infrastructure Operational 10 All agents, VPN/firewall, DW schema, service accounts
Wave 1 Go-Live 23 15–20 mappings, 1K rules, 200 catalog entries, UAT sign-off
Wave 2 Go-Live 33 20 additional mappings, 2K rules, 5M MDM sample validated
Wave 3 Go-Live 41 15 final mappings, 2K final rules, 35M golden records, full lineage
Wave 4 Go-Live (MDM) 45 MDM UAT complete, steward training, production cutover
Project Complete 48 Regression tests passed, hypercare started, project closure

6.3 Production Go-Live Summary

Go-Live # Week Module(s) Business Impact
#1: Wave 1 23 CDI (IBM, Files), CDQ (1K rules), CDGC (200 tables) Manual ETL fully automated; data quality visible
#2: Wave 2 33 CDI (Databases), CDQ (expanded), CDGC (350 tables) 70% data coverage; MDM foundation validated
#3: Wave 3 41 CDI (Cloud), CDQ (complete 5K), CDGC (500 tables, lineage) 100% data integration; full governance
#4: Wave 4 45 MDM Golden records operational; stewardship live

7. CNHI DEPENDENCIES & CRITICAL INPUTS

7.1 Wave 0 Dependencies (Critical Foundation)

If not met by end of Week 10, Wave 1 will slip proportionally.

Dependency Owner Delivery By Impact of Delay
VM Provisioning CNHI IT Infrastructure Week 5 Agent installation delayed; critical path
OS Image & Patching CNHI IT Infrastructure Week 6 Agent installation delayed
Firewall Rules CNHI Security/Network Week 7 Agent connectivity delayed
Service Accounts (SQL Server, SharePoint, file shares) CNHI IT Identity Week 6 Mapping testing delayed; Wave 1 slip
VPN Tunnel Setup (if chosen) CNHI Network + Informatica Week 8 Connectivity validation delayed; performance tuning affected
SQL Server DW Provisioning CNHI IT Infrastructure Week 7 DW design review and testing delayed
Source System Access (IBM, databases, file shares) CNHI Data Stewards/IT Week 6 Data discovery and profiling delayed
Data Quality Rule Inventory CNHI SMEs Week 4 Prioritization and planning delayed; estimated 5K rules
DW Design Sign-Off CNHI Architecture Week 5 Build phase cannot start cleanly
Source Priority Confirmation CNHI Executive Sponsor Week 10 Sprint planning for Wave 1 delayed

7.2 POD 1 Dependencies (CDI+CDQ) — Waves 1–3

Dependency Owner Wave(s) Impact of Delay
Source System Credentials (SQL Server logins, JDBC passwords, API tokens) CNHI IT/Application Owners All waves Mapping tests blocked
Data Quality Rule Specifications (exact validation logic, priority, business context) CNHI SMEs/Data Stewards Wave 1 (Week 11), Wave 2 (Week 24), Wave 3 (Week 34) DQ implementation delayed; reduced pass-rate targets
DW Schema Approval (star-schema design, table/column naming) CNHI DBAs Week 6–7 (before Wave 1 build) Mapping design delayed; Wave 1 slip
Historical Data Availability (10 TB export from sources) CNHI IT/Data Stewards Wave 1 (Week 11) Historical load testing delayed
Mini-UAT Participation (2 weeks per wave) CNHI UAT Team Weeks 21–22 (Wave 1), Weeks 32–33 (Wave 2), Weeks 40–41 (Wave 3) Sign-off delayed; go-live date at risk

7.3 POD 2 Dependencies (MDM) — Waves 2–4

Dependency Owner Wave(s) Impact of Delay
MDM Requirements Workshop (match criteria, survivorship rules, stewardship workflows) CNHI Data Stewards + SMEs Wave 0–1 (Weeks 1–23) MDM design delayed; Wave 2 slip
Sample Data Set (5M beneficiary records, representative providers) CNHI IT/Data Stewards Wave 2 (Week 24) MDM tuning delayed; thresholds not validated
Steward Team Availability (review/approve match results, resolve conflicts) CNHI Data Stewards Wave 2–3 (Weeks 24–41), Wave 4 (Weeks 42–45) Golden record tuning blocked; go-live delayed
MDM Stewardship Training Sutherland Wave 4 (Weeks 42–45) Workflow adoption delayed

7.4 POD 3 Dependencies (CDGC) — Waves 1–5

Dependency Owner Wave(s) Impact of Delay
Business Glossary (domain terms, definitions, mappings to physical assets) CNHI Data Stewards/Domain Leads Wave 1 (Week 11) Catalog search/discovery limited; governance not actionable
Metadata Permissions & Access Model (who sees what in catalog) CNHI IT Security Wave 0 (Week 8) Catalog cannot be deployed; access controls missing
Lineage Acceptance Criteria (what constitutes "complete" end-to-end lineage) CNHI Governance Lead Wave 0 (Week 5) Lineage validation subjective; sign-off delays
Data Classification Rules (PII, confidential, retention) CNHI Security/Compliance Wave 1 (Week 12) Masking policies incomplete; non-prod testing restricted

7.5 Wave 5 Dependencies (Final Integration)

Dependency Owner Due Impact of Delay
UAT Environment Sign-Off (all Waves 1–4 passed testing) CNHI UAT Lead Week 45 Regression testing cannot start
Operator Training Completion CNHI IT Operations Week 47 Hypercare will lack trained responders
Change Management Approvals (CNHI change advisory board) CNHI Change Manager Weeks 46–48 Production cutover delayed; hypercare window shortened

7.6 CNHI Team Requirements Summary

Role / Team Effort Timing Deliverables / Responsibilities
Executive Sponsor 2–3 hrs/week Weeks 0–48 Decision-making authority; escalation; prioritization
IT Director 3–5 hrs/week Weeks 0–10 (Wave 0 peak); ongoing Infrastructure procurement; security approvals; firewall rules
Business SMEs 5–10 hrs/week Waves 0–3 (peak Waves 1–2) DQ rule definitions; business logic validation; UAT
Data Stewards 5–10 hrs/week (Waves 0–2), 15–20 hrs/week (Waves 3–5) Waves 0–5 DQ remediation; MDM validation; golden record approval
DBAs 3–5 hrs/week Waves 0, 5 (peak); ongoing DW design; performance tuning; index strategy
Network/Security 5–10 hrs/week Wave 0 (peak); ongoing VPN tunnel; firewall rules; credential vaulting
UAT Teams 10–20 hrs/week per wave Waves 1–4 (2 weeks per wave) Test case execution; sign-off; defect triage

8. SUCCESS CRITERIA & ACCEPTANCE

8.1 Technical Success Metrics

Metric Target Wave Achievement Measurement Notes
Batch Window ≤3 hours Validated by Wave 5 Job execution duration from start to DW load completion Subject to source availability and network latency
DQ Pass Rate 90% → 95% Wave 1: ≥90%, Wave 2: ≥92%, Wave 3: ≥95% % of records passing all applicable rules per wave Targets are design objectives; actual rates depend on upstream remediation
MDM Match Coverage ≥98% Wave 2: 5M sample validated; Wave 3: 35M+ full load % of input records successfully matched or identified as new "Match coverage" = operational metric; precision/recall tuned during Waves 2–3
Agent Availability 99.5% Operational SLA (active-active HA) Uptime during nightly batch windows Excludes CNHI-side network/source outages
Lineage Completeness 100% source → DW Wave 3 End-to-end lineage for all 50+ mappings Verified via manual audit + lineage reports

8.2 Business Success Criteria

Outcome Wave Enabled Success Definition
Manual ETL Elimination Wave 1 IBM and file-based extracts fully automated; zero manual intervention required nightly
Data Quality Visibility Wave 1 Stewards can see DQ violations in real-time; remediation workflows active
Master Data Readiness Wave 4 Golden records in use by downstream systems; single-view-of-customer operational
Governance & Compliance Wave 3 Catalog searchable; lineage auditable; PDPL compliance demonstrable
Operational Self-Sufficiency Wave 5 CNHI operations team can run, monitor, and troubleshoot platform independently

8.3 Wave-Specific Acceptance Criteria

Wave 0 Exit

  • ✅ All 8 Secure Agents operational and connected to IDMC
  • ✅ VPN tunnel (if chosen) stable with latency < 50 ms
  • ✅ SQL Server DW database created with approved schema
  • ✅ All 4 IDMC module blueprints signed off
  • ✅ Source priorities finalized
  • ✅ DQ rule count confirmed (5K estimate vs. actual)
  • ✅ All PODs ready to sprint

Wave 1 Exit

  • ✅ 15–20 ETL mappings operational and scheduled
  • ✅ 4–5 TB historical data loaded (100% reconciliation)
  • ✅ 1,000 DQ rules live (≥90% pass rate)
  • ✅ 200 tables cataloged
  • PRODUCTION GO-LIVE: Week 23
  • ✅ UAT sign-off received

Wave 2 Exit

  • ✅ 35 total mappings operational
  • ✅ 6–8 TB total data loaded
  • ✅ 3,000 total DQ rules (≥92% pass rate)
  • ✅ 350 tables cataloged
  • ✅ 5M MDM sample successful
  • PRODUCTION GO-LIVE: Week 33

Wave 3 Exit

  • ✅ All 50+ mappings operational
  • ✅ 10 TB total data loaded
  • ✅ 5,000 total DQ rules (≥95% pass rate)
  • ✅ 500 tables cataloged
  • ✅ 35M+ golden records created
  • ✅ Complete end-to-end lineage
  • PRODUCTION GO-LIVE: Week 41

Wave 4 Exit

  • ✅ 35M+ beneficiary golden records operational
  • ✅ 25K+ provider golden records operational
  • ✅ MDM Hub live with stewardship workflows
  • ✅ Stewards trained and confident
  • PRODUCTION GO-LIVE: Week 45

Wave 5 Exit

  • ✅ End-to-end regression testing complete
  • ✅ Performance validated (batch ≤3 hours)
  • ✅ CNHI operations team certified
  • ✅ Hypercare (3 weeks) initiated
  • PROJECT COMPLETE: Week 48

8.4 Deliverable Acceptance Process

Phase Process Timeline
Plan & Design Design documents reviewed and approved by CNHI architecture team 1 week per document
Build & Test Bi-weekly demos; feedback incorporated into next sprint Per sprint (2 weeks)
UAT Mini-UAT (2 weeks per wave) with CNHI business users Per wave
Sign-Off Formal written acceptance signed by CNHI sponsor or designee Before go-live
Hypercare 3-week post-go-live support; issue triage and resolution Weeks 46–48

9. ASSUMPTIONS & RISKS

9.1 Key Assumptions

Assumption Rationale Mitigation
Informatica Windows Server 2022 Support Confirmed CNHI prefers Windows for ops alignment; Informatica may recommend Linux Wave 0 dependency: written confirmation from Informatica before agent provisioning
Source System Access Available Integration requires credentials and connectivity to IBM, SQL Server, SharePoint, APIs, etc. Wave 0 discovery maps all access constraints; Wave 1 onboarding sequence sources with confirmed access
CNHI SME Availability 5–20 hrs/week ongoing participation required Executive sponsor ensures team commitment; steering committee escalates conflicts
Data Quality Rules Estimate (5,000) Indicative; actual scope confirmed post-discovery Wave 0 finalizes rule count; success measured by domain coverage, not rigid count
VPN Tunnel Available IPSec option assumes CNHI network can provision tunnel by Week 8 Fallback: internet egress via port 443 if VPN delayed; performance may vary
SQL Server DW Performance DW tuning (indexes, partitions) assumes CNHI allows Sutherland recommendations Wave 5 performance tuning; CNHI DBA executes recommendations
Secure Agent Capacity Initial 2-agent sizing sufficient for Wave 1–2; scaling available for Wave 3+ Wave 0 capacity planning; elastic scaling model in Wave 5

9.2 Risks & Mitigation

Risk Probability Impact Mitigation
VM Provisioning Delay Medium High (critical path) Weekly dependency tracking; alternate resources available if needed
Source System Credential Challenges Medium High (blocks mapping tests) Wave 0 discovery identifies access constraints; phased onboarding prioritizes available sources
DQ Rule Scope Explosion (actual > 5K) Medium Medium (Wave 1 slip) Wave 0 rule prioritization limits Wave 1 to ~1K; later waves handle excess
MDM Sample Load Performance (slower than expected) Low Medium (Wave 2 slip) Week 24 proof-of-concept; tuning adjustments before full load
Network Latency Issues Low Medium (SLA impact) VPN tunnel provides deterministic path; internet fallback available
Steward Availability for MDM (overcommitted) Medium High (golden record delay) Executive sponsor ensures team commitment; cross-training backup stewards
Informatica Module Feature Loss on Windows Low High (platform switch cost) Wave 0 written confirmation; contingency Linux deployment plan

10. ENGAGEMENT TERMS

10.1 Service Scope & Duration

  • Duration: 48 weeks from contract signature through project closure
  • Sutherland Team: 12–13 FTE specialists (variable per wave; peak Waves 1–3)
  • Engagement Model: Fixed-scope, wave-based delivery with time-box per milestone
  • Change Control: Scope changes managed via change request process; documented impact on timeline/budget

10.2 Warranty & Support

  • Wave 1–4 Warranty: 30 days post-go-live defect rectification at no additional cost
  • Hypercare: 3 weeks post-Wave-5 go-live (Week 46–48) on-call support (2 hrs/day response time)
  • Post-Hypercare SLA: Optional AMS engagement available (separate statement of work)

10.3 Licensing & Informatica Subscriptions

  • IDMC Licenses & IPUs: CNHI responsibility; Sutherland validates sizing against approved scope
  • IPU Adjustment: If scope changes materially (additional sources, rules, data volume), IPU impact will be assessed; cost borne by CNHI
  • License Key Management: CNHI provides; Sutherland configures

10.4 Knowledge Transfer & Training

Training Track Audience Duration Timing
Infrastructure & Operations IT Operations, DBAs 3 days Wave 5 (Weeks 46–47)
Data Integration & Pipelines Developers, data engineers 3 days Wave 1 (post-go-live) + Wave 5 refresher
Data Quality Stewards, SMEs 2 days Wave 1 (post-go-live) + Wave 5
Master Data Management Stewards 2 days Wave 4 (pre-go-live) + Wave 5
Governance & Catalog Business users, stewards 1 day Wave 3 (post-go-live)

10.5 Deliverables Ownership

Deliverable Ownership Post-Project
IDMC Mappings & Configurations CNHI (Sutherland provides runbooks for maintenance)
Data Warehouse Schema & Indexes CNHI DBAs (Sutherland provides tuning recommendations)
Runbooks & Documentation CNHI IT Operations
Source Code (if custom) CNHI (Sutherland retains IP for reusable components)
Lineage & Governance Policies CNHI (Sutherland defines initial structure)

10.6 Commercial Model (To Be Finalized Per RFP)

  • Payment by Wave: Invoices upon milestone completion (Wave 0 Foundation → Wave 5 Closure)
  • Pricing: [To be detailed in commercial proposal section]
  • Optional Post-Project AMS: Separate SOW; includes monitoring, rule updates, new source onboarding, performance tuning

11. FUTURE-READY: AI/LLM & NEXT-GENERATION DATA PIPELINES

Why This Matters

CNHI's enterprise data strategy extends beyond traditional BI into AI-powered decision-making and generative AI applications. Informatica IDMC, combined with Sutherland's implementation approach, creates the governance and data quality foundation that GenAI models depend on.

How IDMC Enables AI/LLM Safety & Trust

AI Challenge IDMC Solution Benefit to CNHI
Data Lineage & Auditability Complete end-to-end lineage (source → transformation → model input) Explainability: trace any model prediction back to its data sources
Data Quality for Model Training 5,000+ DQ rules, pass-rate scorecards Cleaner training data = more accurate models
PII & Sensitive Data Protection Classification tags, masking policies, audit trails Compliant with PDPL; reduces model hallucination risk from PII leakage
Master Data Consistency Golden records (35M+ beneficiaries, 25K+ providers) Stable, deduplicated input to ML models (no bias from duplicate records)
Metadata & Feature Discovery Comprehensive catalog (500+ assets) with glossary mapping Data scientists can rapidly identify features; reduce model development time

Roadmap Examples (Post-Wave-5)

Example 1: Customer Analytics & Churn Prediction

  • Input: Golden beneficiary records (MDM) + transaction data (CDI) + quality-validated flags (CDQ)
  • Model: Train on cleansed, deduplicated data → predict churn risk
  • Transparency: IDMC lineage documents exactly which sources/transformations fed the model

Example 2: Provider Network Optimization

  • Input: Golden provider records (MDM) + service utilization (CDI) + performance metrics (CDQ)
  • Model: Identify underperforming or redundant providers
  • Governance: Classification tags ensure only authorized teams access sensitive provider data

Example 3: LLM Knowledge Repository Hygiene

  • Input: Structured data (beneficiary policies, regulations) + unstructured (documents) → vector store
  • Pipeline: IDMC ensures source data is clean, lineage-tracked, masked where needed
  • Governance: Audit trail of what data went into knowledge base (critical for RegTech compliance)

Implementation Considerations (Post-Wave-5 Engagement)

Area Who Owns How IDMC Helps
Data Preparation for ML CNHI Data Science + Sutherland (optional AMS) IDMC lineage & DQ provide clean inputs; reduce prep time
LLM Prompt Engineering CNHI Data Science Catalog + lineage visibility help identify features for few-shot examples
Model Monitoring & Drift CNHI Operations + Data Science IDMC metadata & DQ continue tracking source data quality post-model
Compliance & Audit CNHI Compliance + Governance IDMC lineage & classification tags simplify PDPL/audit responses

12. REFERENCES & CREDENTIALS

12.1 Sutherland Expertise

Informatica & Enterprise Data Integration:

  • 15+ years of data platform implementations across EMEA, Asia-Pacific, and Americas
  • 50+ greenfield data warehouse and ETL modernization projects
  • Certified Informatica implementation partners (CDI, CDQ, MDM, CDGC modules)
  • Expertise in regulated industries: healthcare, financial services, government, telecommunications

Data Governance & Compliance:

  • Experience implementing PDPL, GDPR, CCPA-aligned governance frameworks
  • Catalog and lineage implementations supporting audit and compliance
  • Master data management for identity resolution in regulated contexts

Regional Presence:

  • Established operations in Middle East and North Africa (MENA)
  • Local security clearance and compliance certifications
  • Hybrid (onshore/offshore) delivery model with MENA-based support teams

12.2 Proposed Team Certifications

  • Solution Architect: Informatica Certified Professional (CDI/CDQ/MDM), AWS or Azure Cloud Architect
  • POD Leads: Informatica Certified Developers (module-specific)
  • All Team Members: Relevant cloud and security certifications (e.g., AWS Security, ISO 27001)

12.3 Reference Case Studies (Anonymized)

[Case Study 1: Healthcare Provider Integration]

  • Client: Large Middle Eastern healthcare network (~500 hospitals)
  • Challenge: 20+ source systems; fragmented patient records; compliance with local data residency laws
  • Solution: IDMC + Sutherland; greenfield master patient index (30M+ records); 100% on-premises execution
  • Result: 15% reduction in duplicate encounters; improved care coordination; PDPL-ready governance

[Case Study 2: Financial Services Master Data]

  • Client: Regional bank (KSA-based; confidential NDA)
  • Challenge: Multiple acquired banks; duplicate customer records; legacy core systems
  • Solution: IDMC MDM; survivorship rules; stewardship workflows
  • Result: Single customer view; 40% faster new product deployment; 25% reduction in risk management effort

13. EVALUATION & SELECTION CRITERIA

13.1 How Sutherland Differentiates

Dimension Sutherland's Approach
Delivery Speed & Early Value Parallel POD model delivers first production value Week 23 (not Week 52+); four incremental go-lives reduce risk
Data Sovereignty & PDPL Compliance 100% on-premises execution; zero raw data moves to cloud; IDMC is orchestration only; transparent architecture
Operational Readiness Hypercare + runbooks + training focus on CNHI self-sufficiency; not a "hand-off and abandon" approach
AI/LLM Future-Readiness Governance, lineage, and data quality framework positions CNHI for safe, compliant GenAI pipelines
Hybrid Delivery Model Combination of onshore expertise (Riyadh/KSA presence) and offshore scaling (India-based centers) maximizes efficiency and cost
Fixed-Wave Commitment 48-week roadmap with gated, achievable milestones; reduced scope creep via sprint discipline

13.2 Proposed Pricing Model (Illustrative)

Structure: Fixed-price, milestone-based payment per wave

Phase Duration Deliverables Proposed Cost
Wave 0 Weeks 1–10 Foundation, discovery, DW design, infrastructure [TBD]
Wave 1 Weeks 11–23 CDI+CDQ, first production go-live [TBD]
Wave 2 Weeks 24–33 Core databases, MDM sample, second go-live [TBD]
Wave 3 Weeks 34–41 Cloud sources, complete CDGC, third go-live [TBD]
Wave 4 Weeks 42–45 MDM production deployment [TBD]
Wave 5 + Hypercare Weeks 46–48 Regression, optimization, 3-week hypercare [TBD]
TOTAL (48 weeks) Full end-to-end implementation [TBD]

Optional Post-Project:

  • Managed Services (AMS): 12-month support, monitoring, rule updates, new source onboarding — [TBD] per month

APPENDIX: CRITICAL SUCCESS FACTORS

For Sutherland

  1. Secure Wave 0 completion on time — any delay cascades
  2. Maintain parallel POD momentum — weekly syncs essential; dependencies tracked daily
  3. Demonstrate tangible Wave 1 value — Week 23 go-live builds credibility for Waves 2–5
  4. Steward engagement during Waves 2–4 — golden record success depends on steward availability

For CNHI

  1. Executive sponsor empowered to remove roadblocks — VMs, firewall, credentials, approvals
  2. SME and steward time commitment — cannot be ad-hoc; must be prioritized
  3. Data governance model clarification in Wave 0 — enables faster governance implementation
  4. Source system access confirmed early — prevents mid-wave surprises

CLOSING STATEMENT

This proposal outlines a pragmatic, risk-managed path to transforming CNHI's data capabilities. By combining Informatica IDMC's cloud-based orchestration with on-premises Secure Agents and parallel POD delivery, Sutherland will:

Deliver first production value in Week 23 (not 52+ weeks)
Ensure 100% data residency in Saudi Arabia (PDPL-compliant)
Automate manual ETL, establish data quality, and enable master data management
Catalog and govern 500+ data assets with complete lineage
Build a foundation for safe, trustworthy AI/LLM pipelines
Hand over operational control to CNHI by Week 48 with confidence

The roadmap is ambitious yet achievable, grounded in Sutherland's 15+ years of enterprise data platform expertise and commitment to CNHI's success.


Document Version: 1.0
Date: January 2, 2026
Prepared by: Sutherland Presales Analytics Solution Team
For: CNHI Executive Leadership & RFP Evaluation Committee